M/S PRATAP CONSTRUCTION PURENDARPUR AND ANOTHER v. STATE OF UP AND 3 OTHERS
WRIC/31551/2025 · 2025-09-09
Arun Kumar, Manoj Kumar Gupta
body2025
DailyLaw.ai
[ 2025 DAILYLAW 94694 (ALL) · dailylaw.ai ]
DailyLaw.ai
[ 2025 DAILYLAW 94694 (ALL) · dailylaw.ai ]
Judgment text
Extracted from the PDF above. The PDF is authoritative.
HIGH COURT OF JUDICATURE AT ALLAHABAD WRIT - C No. - 31551 of 2025 Court No. - 21 HON'BLE MANOJ KUMAR GUPTA, J.
HON'BLE ARUN KUMAR, J.
1. The case of the petitioners is that they have duly completed work in pursuance of agreement dated 18.10.2021 and 03.01.2022 between the parties. The second and final bill was duly verified by the concerned Engineer but its payment has not been made so far. The representation filed by the petitioners in this regard is stated to be pending.
2. The submission is that the same be directed to be decided.
3. Shri Rajiv Gupta, learned Additional Chief Standing Counsel has no objection to the same.
4. Accordingly, the writ petition is disposed of with direction to respondent no.4 to decide the representation dated 26.07.2025 within eight weeks from the date of communication of the instant order alongwith photostat copy of the representation. September 10, 2025 Ankit. Versus Counsel for Petitioner(s) : V.K.Singh Counsel for Respondent(s) : C.S.C. (Arun Kumar,J.) (Manoj Kumar Gupta,J.) M/S Pratap Construction Purendarpur And Another .....Petitioner(s) State Of Up And 3 Others .....Respondent(s) Digitally signed by :- ANKIT VISHWAKARMA High Court of Judicature at Allahabad