Research › Search › Judgment

High Court of Punjab and Haryana · body

2025 DAILYLAW 87762 (PNJ)

NACHHATTAR SINGH KULAR v. SAKSHI SWAHNEY

COCP/3306/2024 · 2025-07-30

Harkesh Manuja

body2025

Judgment text

Extracted from the PDF above. The PDF is authoritative.

COCP No.3306 of 2024 IN THE HIGH COURT OF PUNJAB AND HARYANA 152 NACHHATTAR SINGH KULAR Vs SAKSHI SWAHNEY CORAM: HON'BLE MR. JUSTICE HARKESH MANUJ Present: Mr. for the petitioner. Mr. Athar Ahmed, DAG, Pu HARKESH MANUJA, J. (Oral) 1. Additional affidavit of Himanshu Jain, Deputy Commissioner, Ludhiana filed on behalf of the respondent has been filed in Court, the same is taken on record. Relevant para No.6 extracted therefrom is “6. passed by this Hon’ble Court, the Executive Engineer, Panchayati Raj Public Works Division, Ludhiana, alongwith the Development Officer, Junior Engineer and the Sub Divisional Officer, Panchayati Raj, After carrying out the necessary measurements at the spot in the village of the fields of the petitioner from which the pipeline carrying excess water from the fields of the petitioner to the int be done and the expenditure involved in carrying out the en calculated as Rs. Panchayati Raj Public Works Division, Ludhiana has submitted his report along with Panchayat Officer, Ludhiana vide his letter No. 02/03/2006 dated 24/07/2025. True translated copy of the said letter dated 24/07/2025 along with the detailed estimate prepared as well as the pr the pipeline for disposal of rain water from the fields of the petitioner is attached herewith as Annexure A 2024 (O&M) IN THE HIGH COURT OF PUNJAB AND HARYANA AT CHANDIGARH COCP No.3306 of 2024 (O&M) Date of Decision: NACHHATTAR SINGH KULAR SAKSHI SWAHNEY HON'BLE MR. JUSTICE HARKESH MANUJ Mr. Divyam Singh, Advocate for the petitioner. Mr. Athar Ahmed, DAG, Punjab. **** HARKESH MANUJA, J. (Oral) Additional affidavit of Himanshu Jain, Deputy Commissioner, Ludhiana filed on behalf of the respondent has been filed in Court, the same is taken on record. Relevant para No.6 extracted therefrom is That in compliance of the above reproduced order dated 09/07/2025 passed by this Hon’ble Court, the Executive Engineer, Panchayati Raj Public Works Division, Ludhiana, alongwith the Development Officer, Junior Engineer and the Sub Divisional Officer, Panchayati Raj, Jagraon, had visited the spot in the village on 21/07/2025. After carrying out the necessary measurements at the spot in the village of the fields of the petitioner from which the pipeline carrying excess water from the fields of the petitioner to the int be done and the expenditure involved in carrying out the en calculated as Rs.3,32,000/-. Thereafter, the Executive Engineer, Panchayati Raj Public Works Division, Ludhiana has submitted his report along with all the above stated documents to the District Development and Panchayat Officer, Ludhiana vide his letter No. 02/03/2006 dated 24/07/2025. True translated copy of the said letter dated 24/07/2025 along with the detailed estimate prepared as well as the pr the pipeline for disposal of rain water from the fields of the petitioner is attached herewith as Annexure A-5.” IN THE HIGH COURT OF PUNJAB AND HARYANA AT CHANDIGARH COCP No.3306 of 2024 (O&M) Date of Decision: 30.07.2025 ......Petitioner ....Respondent HON'BLE MR. JUSTICE HARKESH MANUJA Additional affidavit of Himanshu Jain, Deputy Commissioner, Ludhiana filed on behalf of the respondent has been filed in Court, the same is taken on record. Relevant para No.6 extracted therefrom is extracted hereinunder: ove reproduced order dated 09/07/2025 passed by this Hon’ble Court, the Executive Engineer, Panchayati Raj Public Works Division, Ludhiana, alongwith the Sarpanch, Village Development Officer, Junior Engineer and the Sub Divisional Officer, Jagraon, had visited the spot in the village on 21/07/2025. After carrying out the necessary measurements at the spot in the village of the fields of the petitioner from which the pipeline carrying excess water from the fields of the petitioner to the intercepting drain, the total work to be done and the expenditure involved in carrying out the entire work was . Thereafter, the Executive Engineer, Panchayati Raj Public Works Division, Ludhiana has submitted his report all the above stated documents to the District Development and Panchayat Officer, Ludhiana vide his letter No. 02/03/2006 dated 24/07/2025. True translated copy of the said letter dated 24/07/2025 along with the detailed estimate prepared as well as the proposed plan for laying the pipeline for disposal of rain water from the fields of the petitioner is 1 Additional affidavit of Himanshu Jain, Deputy Commissioner, Ludhiana filed on behalf of the respondent has been filed in Court, the same is hereinunder:- ove reproduced order dated 09/07/2025 passed by this Hon’ble Court, the Executive Engineer, Panchayati Raj Sarpanch, Village Development Officer, Junior Engineer and the Sub Divisional Officer, Jagraon, had visited the spot in the village on 21/07/2025. After carrying out the necessary measurements at the spot in the village of the fields of the petitioner from which the pipeline carrying excess water ercepting drain, the total work to tire work was . Thereafter, the Executive Engineer, Panchayati Raj Public Works Division, Ludhiana has submitted his report all the above stated documents to the District Development and Panchayat Officer, Ludhiana vide his letter No. 02/03/2006 dated 24/07/2025. True translated copy of the said letter dated 24/07/2025 along oposed plan for laying the pipeline for disposal of rain water from the fields of the petitioner is MOHMED ATIK 2025.07.30 17:07 I attest to the accuracy and authenticiy of this order/judgment COCP No.3306 of 2024 2. In view thereof, petitioner, who is present in Court has handed over a cheque bearing No.803948 dated 30.07.2025 Indian Overseas Bank in favour of XEN (P.R.) Ludhiana J.E., who is also present in Court. 3. Learned State counsel on instructions assures that process of laying down of pipes shall be initiated concluded within a month thereafter. 4. In such circumstances, no cause survives in the instant petition. The same stands disposed of. of. 5. Rule stands discharged. July 30, 2025 Atik Whether speaking/reasoned Whether reportable 2024 (O&M) In view thereof, petitioner, who is present in Court has handed over a cheque bearing No.803948 dated 30.07.2025 in Indian Overseas Bank in favour of XEN (P.R.) Ludhiana , who is also present in Court. Learned State counsel on instructions assures that process of laying down of pipes shall be initiated within four days from today and the same shall be concluded within a month thereafter. In such circumstances, no cause survives in the instant petition. The same stands disposed of. Pending application(s), if any, shall also stand disposed le stands discharged. (HARKESH MANUJA) Whether speaking/reasoned Yes/No Whether reportable Yes/No In view thereof, petitioner, who is present in Court has handed over a in a sum of Rs.3,32,000/- drawn at Indian Overseas Bank in favour of XEN (P.R.) Ludhiana to Sh. Mohandeep Singh, Learned State counsel on instructions assures that process of laying within four days from today and the same shall be In such circumstances, no cause survives in the instant petition. The Pending application(s), if any, shall also stand disposed (HARKESH MANUJA) JUDGE Yes/No Yes/No 2 In view thereof, petitioner, who is present in Court has handed over a drawn at to Sh. Mohandeep Singh, Learned State counsel on instructions assures that process of laying within four days from today and the same shall be In such circumstances, no cause survives in the instant petition. The Pending application(s), if any, shall also stand disposed MOHMED ATIK 2025.07.30 17:07 I attest to the accuracy and authenticiy of this order/judgment