Page No.# 1/3 GAHC010035802024
2025:GAU-AS:3460
THE GAUHATI HIGH COURT (HIGH COURT OF ASSAM, NAGALAND, MIZORAM AND ARUNACHAL PRADESH) Case No. : WP(C)/901/2024 ABDUL BACHIT S/O LATE HAZI TAFAZZUL ALI RESIDENT OF VILLAGE KABARIBUND, PO AND PS PATHARKANDI, DIST KARIMGANJ, ASSAM VERSUS THE GOVT OF ASSAM AND 6 ORS REPRESENTED BY THE SECRETARY PUBLIC WORKS DEPARTMENT, DISPUR, GUWAHATI 781006 2:THE GOVT. OF ASSAM REPRESENTED BY THE COMMISSIONER AND SECRETARY HEALTH AND FAMILY WELFARE DEPARTMENT DISPUR GUWAHATI 781006 3:THE GOVT. OF ASSAM REPRESENTED BY THE COMMISSIONER AND SECRETARY FINANCE DEPARTMENT DISPUR GUWAHATI 781006 4:THE DIRECTOR NATIONAL RURAL HEALTH MISSION CHRISTIAN BASTI GUWAHATI 781006 ASSAM 5:THE SPECIAL CHIEF ENGINEER PUBLIC WORK DEPARTMENT (BUILDING) HEALTH AND EDUCATION ASSAM CHANDMARI GUWAHATI 781003 6:THE CHIEF ENGINEER PUBLIC WORKS DEPARTMENT BUILDING ASSAM CHANDMARI
Page No.# 2/3 GUWAHATI 781003 7:THE EXECUTIVE ENGINEER PUBLIC WORKS DEPARTMENT KARIMGANJ DISTRICT TERRITORIAL BUILDING DIVISION KARIMGANJ Advocate for the Petitioner : MR. B J GHOSH, MR. T SK,MR. I ALAM Advocate for the Respondent : SC, PWD, SC, NRHM,SC, HEALTH,SC, FINANCE
BEFORE HONOURABLE MR. JUSTICE LANUSUNGKUM JAMIR
ORDER Date : 26.03.2025
Heard Mr. B. J. Ghosh, learned counsel for the petitioner.
2. Pursuant to a Press Notice dated 20.10.2014, the petitioner submitted his bid for the work “Upgradation of SC/SD/PHC to Community Health Centre Phase-I in Barak Valley under CM’s Special Package under Annual Plan 2013-14”. The bid of the petitioner was accepted and the Chief Engineer, PWD (Building), Assam, issued “Issue of notice to proceed with the work” on 07.03.2015 to the petitioner with regard to the said package. The petitioner, accordingly, completed the entire work on 30.09.2021 and handing and taking over also took place on 04.01.2022. A completion certificate was also issued by the Executive Engineer, PWD, Karimganj District Territorial Building Division, which was countersigned by the Assistant Executive Engineer, PWD., Ratabari & Patherkandi. Thereafter, the petitioner submitted his final bill on 15.03.2022 for an amount of Rs.3,29,82,720/-. The Executive Engineer, PWD, Silchar, Sonai & Dholai Territorial Building Division also sent a proposal for revalidation of administrative approval for the said work to the Chief Engineer, PWD Building,
Page No.# 3/3 Health and Education, Assam on 12.09.2022. However, as the said outstanding due has not been paid to the petitioner, the petitioner is before this Court by way of the present writ petition.
3. Mr. B. Gogoi, learned Standing Counsel, PWD and Health Department, on instructions from the respondent No. 7, submits that the outstanding due is an admitted amount, however, he submits that the Authorities may be allowed to re-verify and thereafter, pay the said admitted amount within a specific period of time.
4. After hearing the learned counsel for the parties, this writ petition is
disposed of directing the respondents to have a re-verification with regard to the outstanding dues claimed by the petitioner and thereafter, pay the admitted amount to the petitioner within a period of 4 (four) months from the date of receipt of a certified true copy of this Court’s Order.
5. With the above observations and directions, this writ petition is disposed of.
JUDGE Comparing Assistant