HIGH COURT LEGAL SERVICES COMMITTEE, BENGALURU BEFORE THE NATIONAL LOK ADALAT
IN THE HIGH COURT OF KARNATAKA AT BENGALURU
DATED THIS THE 26TH DAY OF APRIL, 2025
CONCILIATORS PRESENT:
THE HON'BLE MR. JUSTICE B M SHYAM PRASAD
&
SRI. B.S. PRASAD, MEMBER
W.P. No.1621/2019 (Lok Adalat No.932/2025)
BETWEEN:
SHIVANANDA POOJARY S/O AVANNA POOJARY, AGED ABOUT 44 YEARES, R/AT VIVEKANANDA NAGAR, HOSPET LANE, INDI TALUK, BIJAPUR DISTRICT. ...PETITIONER
(BY SRI. SHEKAR L., ADVOCATE)
AND:
THE DIVISIONAL CONTROLLER K.S.R.T.C., PUTTUR DIVISION, PUTTUR-575 201. …RESPONDENT (BY SRI. R.B. ANNEPANNAVAR, ADVOCATE)
2
THIS WRIT PETITION IS FILED UNDER ARTICLE 226 AND 227 OF THE CONSTITUTION OF INDIA PRAYING TO QUASH THE ORDER DATED 09.10.2017 ON ISSUE NO.1 VIDE ANEXURE-A AND ALSO THE IMPUGNED AWARD DATED 29.12.2017 PASSED BY THE LEARNED PRESIDING OFFICER, LABOUR COURT, DAKSHINA KANNADA, MANGALORE IN IDA NO.3/2017 VIDE ANNEXURE-B TO THE WRIT PETITION. THIS WRIT PETITION COMING ON FOR CONCILIATION BEFORE NATIONAL LOK ADALAT, THE FOLLOWING CONCIALIATION ORDER IS PASSED:
CONCILIATION ORDER
In this petition, the petitioner has prayed for quashing the Award dated 29.12.2017 passed by the learned Presiding Officer, Labour Court, Dakshina Kannada, Mangalore in IDA No.3/2017 vide Annexure - B.
2. After negotiations, the parties have arrived at settlement. Both the parties have filed a Joint Memo
3 duly signed before the Lok Adalath. The said Joint Memo reads as follows:
1. The Respondent – Corporation agreed to reinstate the Respondent – workman into service without continuity of service, without consequential benefits without backwages from the date of dismissal till the date of actual reinstatement subject to production of fitness certificate by the petitioner only. 2. The parties to the proceedings have agreed for the above terms. 3. Accordingly, this Writ Petition is disposed of in terms of the Joint Memo modifying the Award dated 29.12.2017 passed by the learned Presiding Officer, Labour Court, Dakshina Kannada, Mangalore in IDA No.3/2017 vide Annexure-B.
Sd/-
JUDGE
Sd/- MEMBER nv
4 FILED BEFORE LOK ADALAT HIGH COURT LEGAL SERVICES COMMITTEE,BENGALURU BEFORE THE HIGH COURT LOK ADALAT WP.NO.1621/2019 (LOK ADALAT NO. 932/2025)
BETWEEN SHIVANANDA POOJARY
…Petitioner
AND:
THE DIVISIONAL CONTROLLER, KSRTC
…Respondent
JOINT MEMO
The WP filed against the award in IDA.No.03/2017 dated 29.12.2017 on the file of the Presiding Officer, Labour Court, Mangalore has been settled between the parties on the following terms and the award may kindly be modified as under:
1.
The Respondent – Corporation agreed to reinstate the Respondent – workman into service without continuity of service, without consequential benefits without backwages from the date of dismissal till the date of actual reinstatement subject to production of fitness certificate by the petitioner only. 2. The parties to the proceedings have agreed for the above terms. The parties to this petition have set their hands to this settlement before the Lok Adalat in the presence of Conciliators on this 26.04.2025 at Bengaluru Bench. Sd/-
Sd/- SIGNATURE OF PETITIONER SIGNATURE OF RESPONDENT
Sd/-
Sd/- ADVOCATE FOR PETITIONER ADVOCATE FOR RESPONDENT/S