THE EXECUTIVE ENGINEER, IRRIGATION PROJECT, MAJBUTIKARAN DIVISION, v. BARKUBAI NAGNATH BAVKAR

CA/3097/2023 · 2025-02-21

Shri R M Joshi

body2025

Judgment text

Extracted from the PDF above. The PDF is authoritative.

IN THE HIGH COURT OF JUDICATURE AT BOMBAY BENCH AT AURANGABAD CIVIL APPLICATION NO. 3097 OF 2023 IN FAST/2835/2023 THE EXECUTIVE ENGINEER, IRRIGATION PROJECT, MAJBUTIKARAN DIVISION, VERSUS BARKUBAI NAGNATH BAVKAR ….. WITH CIVIL APPLICATION NO. 3105 OF 2023 IN FAST/2847/2023 THE EXECUTIVE ENGINEER, IRRIGATION PROJECT, MAJBUTIKARAN DIVISION, VERSUS MAHADEO VISHWANATH BAVKAR WITH CIVIL APPLICATION NO. 3101 OF 2023 IN FAST/2844/2023 THE EXECUTIVE ENGINEER, IRRIGATION PROJECT, MAJBUTIKARAN DIVISION, VERSUS JAMIR ALAM SHAIKH WITH CIVIL APPLICATION NO. 3099 OF 2023 IN FAST/2838/2023 THE EXECUTIVE ENGINEER, IRRIGATION PROJECT, MAJBUTIKARAN DIVISION, VERSUS MANIK NAGNATH SOMWANSHI ….. WITH CIVIL APPLICATION NO. 3103 OF 2023 IN FAST/2841/2023 THE EXECUTIVE ENGINEER, IRRIGATION PROJECT, MAJBUTIKARAN DIVISION, VERSUS MAHADEO MALAPPA KAPASE 935.ca3097.23.odt 1 of 2 2025:BHC-AUG:5038 Mr. G. B. Rajale, Advocate for Applicant Ms. S. A. Kale h/f Mr. A. B. Kale, Advocate for respondent No.1. CORAM : R. M. JOSHI, J. DATE : 21st FEBRUARY, 2025 PER COURT :- 1. These applications are filed for condonation of delay in filing First Appeal against the judgment and award passed by Reference Court in respect of land acquisition. 2. Learned counsel for the appellant submits that in connected appeals, similar delay is condoned by this Court. 3. Learned counsel for the respondent opposed the applications. 4. For the reasons mentioned in the applications and also in view of the fact that in connected appeals the delay is condoned, this Court finds no reason to reject the applications. 5. Hence, applications are allowed in above terms. 6. First Appeals be registered. (R. M. JOSHI, J.) ssp 935.ca3097.23.odt 2 of 2