Neutral Citation No. - 2025:AHC:110746-DB Court No. - 29 Case :- WRIT - C No. - 21642 of 2025 Petitioner :- Chandra Pal Respondent :- Union Of India And 3 Others Counsel for Petitioner :- Rateesh Singh,Shriprakash Yadav Counsel for Respondent :- A.S.G.I.,Anurag Yadav,C.S.C. Hon'ble Mahesh Chandra Tripathi,J. Hon'ble Vinod Diwakar,J.
1. Heard Shri Rateesh Singh, learned counsel for the petitioner; Shri Ambrish Shukla, learned Addl. Chief Standing Counsel for State respondents and Shri Anurag Yadav for National Highway Authority of India (in short "NHAI"). Shri R.K. Jaiswal appears for Union of India and vakalatnama filed by him has been taken on record. 2. The instant writ petition has been preferred for a direction to respondents to make payment of compensation of additionally acquired area of 0.075 hect. in excess to published area of 0.125 hect. of plot no.112/3 situated in Village Nagla Umed, Tehsil Sasani, Distt. Hathras and for a further direction to respondent no.2-District Magistrate, Hathras to decide the representation/ reminder of the petitioner dated 07.05.2025 within stipulated period. 3. Learned counsel for the petitioner has contended that the petitioner is recorded bhumidhar with transferable right of plot no.112/3 area 0.2062 hect. situated in Village Nagdla Ummed, Tehsil Sasani, Distt. Hathras. In support of his submissions, he has placed reliance on relevant khatauni of Fasli Year 1430-1435, which is annexed as Annexure No.1 to the writ petition. A notification was published under Section 3A and 3D of National Highway Act on 02.11.2021 for construction of national highway. It is alleged that even though part of land of the petitioner had been acquired but the NHAI had utilised the excess land. In support of his submissions, he has placed reliance on the communication dated 08.08.2022 sent by the Addl. District Magistrate (F&R), Hathras to the Project Director, NHAI, wherein it is informed that after verifying the record and measurement on the spot, it had been found that excess land had been utilised for laying the national highway and further request was made to Project Director, NHAI for reconciling the record. 4. Learned counsel for the petitioner, in this backdrop, submits that on spot revenue officials had measured the land and admittedly excess land had been utilised by NHAI in laying the national highway. But inspite of the report dated 08.08.2022, till date the actual compensation has not been paid qua excess land, which has been utilised by NHAI.
Learned counsel for the petitioner has confined his prayer for a direction to NHAI to ensure adequate compensation in lieu of land, which has been utilised by NHAI. 5. Learned counsel for NHAI has resisted the relief on the premise that National Highway Act (in short "Act") is self-contained, wherein full fledged mechanism is provided. In case the petitioner is aggrieved, he has remedial forum under the Act to press the relief before the Arbitrator. So far as communication dated 08.08.2022 is concerned, at present, he is not in a position to controvert the said communication. As such some breathing time may be accorded to address in this regard. 6. Considering the factual situation, we are not inclined to adjudicate in the instant matter at this stage. Once revenue officials had made detailed survey on the spot and made necessary communication in this regard to Project Director, NHAI on 08.08.2022, no justifiable response has been shown to us that
inspite of notice to NHAI what remedial measures had been taken by NHAI. 7. In the facts and circumstances, we find that in response to the communication dated 08.08.2022, the competent authority of NHAI must consider the grievance of the petitioner and, if necessary, again survey on spot in the presence of the petitioner and in case any excess land has been utilised by NHAI for laying the national highway, definitely the appropriate order will be passed in accordance with law expeditiously and preferably within three months from the date of production of certified copy of this
order but certainly after giving fullest opportunity to the petitioner.
8. The writ petition stands disposed of accordingly.
Order Date :- 10.7.2025 SP/ Digitally signed by :- SURYA PRAKASH High Court of Judicature at Allahabad