Research › Search › Judgment

High Court of Chhattisgarh · body

2025 DAILYLAW 7004 (CHH)

M/S RAMGOPAL SOMANI v. MUNICIPAL CORPORATION, RAIGARH

WPC/760/2025 · 2025-02-05

Shri Bibhu Datta Guru

body2025

Judgment text

Extracted from the PDF above. The PDF is authoritative.

1 / 2 2025:CGHC:6488 HIGH COURT OF CHHATTISGARH AT BILASPUR WPC No. 760 of 2025 1 - M/s Ramgopal Somani Through Power of Attorney Holder Varun Somani, Aged About 36 Years, S/o Shri Ramgopal Somani, At- Station Road, Champa, District Janjgir Champa, Chhattisgarh ... Petitioner(s) versus 1 - Municipal Corporation, Raigarh Through Commissioner, Municipal Corporation, Raigarh, Pin- 496001 2 - Executive Engineer Municipal Corporation, Raigarh, Pin- 496001 3 - Assistant Engineer Municipal Corporation, Raigarh, Pin- 496001 ... Respondents (Cause title is taken from Case Information System) For Petitioner : Mr. Akash Mishra, Advocate For Respondents : Mr. Rakshit Tiwari, Advocate on behalf of Mr. Pankaj Agrawal, Advocate (HON’BLE SHRI JUSTICE BIBHU DATTA GURU) Order on Board 05/02/2025 1. By the present writ petition, the petitioner is seeking a direction towards the respondent/Corporation to release the dues towards the work done by the petitioner pursuance to the order dated 11/02/2016. AMARDEEP CHOUBEY Digitally signed by AMARDEEP CHOUBEY Date: 2025.02.07 17:00:32 +0530 2 / 2 2. Learned Counsel for the petitioner submits that pursuance to the work order dated 11/02/2016, the petitioner has completed the work which is reflected from the Work Completion Certificate dated 30/03/2016 vide Annexure P-4, however, the respondents/Corporation are not making payment of the dues towards the bill raised by the petitioner. 3. Learned counsel for the respondents/Corporation submits that the Commissioner/Municipal Corporation shall verify and examine the grievance raised by the petitioner and if the work allotted to the petitioner has been completed and the amount is undisputed, the same shall be released within a period of two months from the date of receipt of a copy of this order. 4. I have heard learned counsel for both the parties and perused the pleadings. 5. Having considered the submissions raised by the learned counsel for the parties, the writ petition is disposed of with a direction to the Commissioner, Municipal Corporation, Raigarh to verify and examine the grievance of the petitioner and if the work allotted to the petitioner has been completed and the dues claimed by the petitioner is undisputed, the same be released within a period of two months from the date of receipt of a copy of this order. 6. With the aforesaid direction, this writ petition is disposed of. SD/- (BIBHU DATTA GURU) JUDGE Amardeep