Research › Search › Judgment

Bombay High Court · body

2025 DAILYLAW 6739 (BOM)

Executive Engineer Seena Kolegaon Project v. Dashrath Babu Miskin and Ors

CA/989/2025 · 2025-04-17

Shri S G Chapalgaonkar

body2025

Judgment text

Extracted from the PDF above. The PDF is authoritative.

(1) 74-ca-989-2025.odt IN THE HIGH COURT OF JUDICATURE AT BOMBAY BENCH AT AURANGABAD CIVIL APPLICATION NO. 989 OF 2025 IN FAST/2150/2025 EXECUTIVE ENGINEER SEENA KOLEGAON PROJECT VERSUS DASHRATH BABU MISKIN AND ORS ... Mr. Deepak B. Rasve h/f Mr. Chetan Trimbakrao Jadhav, Advocate for Applicant. Mr. D. B. Bhange, AGP for Respondents-State. ... CORAM : S. G. CHAPALGAONKAR, J. DATED : 17th APRIL, 2025. P.C.:- 1. Heard learned Advocates appearing for respective parties. 2. By this application, applicant seeks to condone delay of 388 days caused in filing appeal against award passed by Reference Court. 3. Perused reasons as stated in application. The delay appears to have been caused on account of administrative exigency. The applicant has not derived any advantage by making such delay. Hence, sufficient cause is made out to condone delay. Hence, following order: ORDER a. Civil Application is allowed. b. Delay of 388 days caused in filing appeal is hereby condoned. c. Appeal be registered subject to removal of office objections. (S. G. CHAPALGAONKAR) JUDGE Devendra/April-2025 2025:BHC-AUG:11174