M/S. SHREE BAJRANG BALI CONTRACT COMPANY AND 3 OTHERS v. UNION OF INDIA AND 4 OTHERS
WRIC/19553/2025 · 2025-07-09
Manoj Kumar Gupta, Ram Manohar Narayan Mishra
body2025
DailyLaw.ai
[ 2025 DAILYLAW 67008 (ALL) · dailylaw.ai ]
DailyLaw.ai
[ 2025 DAILYLAW 67008 (ALL) · dailylaw.ai ]
Judgment text
Extracted from the PDF above. The PDF is authoritative.
Neutral Citation No. - 2025:AHC:110799-DB Court No. - 21 Case :- WRIT - C No. - 19553 of 2025 Petitioner :- M/S. Shree Bajrang Bali Contract Company And 3 Others Respondent :- Union Of India And 4 Others Counsel for Petitioner :- Rekha Singh,Sanjeev Singh Counsel for Respondent :- A.S.G.I.,Prem Narayan Rai Hon'ble Manoj Kumar Gupta,J. Hon'ble Ram Manohar Narayan Mishra,J.
1. Heard Sri Sanjeev Singh, learned counsel for the petitioners and Sri Prem Narayan Rai, learned counsel for the respondents.
2. The petitioners are aggrieved by the order dated 8th May, 2025, by which the contract has been determined in terms of Clause-62 of Standard General Conditions of Contract.
3. Sri Sanjeev Singh, learned counsel for the petitioners submits that the petitioners could not complete the work on account of disruptions during Kumbh Mela. He submits that the petitioners would submit their detailed representation and pray for extension of time under the contract and the same be directed to be decided.
4. Sri Prem Narayan Rai, learned counsel appearing on behalf of the Railways very fairly states that in case any representation is filed by the petitioner, it will be taken into consideration.
5. Accordingly, the petition is disposed of with liberty to the petitioners to make representation within three days alongwith attested copy of the instant order, and in which event, the same will be considered and decided by respondent No.5 within next one week. Order Date :- 10.7.2025 Ashish/- (R.M.N.Mishra, J.) (Manoj Kumar Gupta, J.) Digitally signed by :- ASHISH KUMAR SINGH High Court of Judicature at Allahabad