Research › Search › Judgment

Bombay High Court · body

2025 DAILYLAW 6606 (BOM)

Maharashtra State Electricity Distribution Company Through Junior Engineer Rural Purna and anr v. Sunita Rameshwar Ambore and Ors

CA/748/2025 · 2025-04-15

Shri S G Chapalgaonkar

body2025

Judgment text

Extracted from the PDF above. The PDF is authoritative.

1 169-ca-748-2025 IN THE HIGH COURT OF JUDICATURE AT BOMBAY BENCH AT AURANGABAD CIVIL APPLICATION NO. 748 OF 2025 IN FAST/1967/2025 Maharashtra State Electricity Distribution Company Through Junior Engineer Rural Purna And Anr VERSUS Sunita Rameshwar Ambore And Ors WITH CIVIL APPLICATION NO. 749 OF 2025 IN FAST/1967/2025 Maharashtra State Electricity Distribution Company Through Junior Engineer Rural Purna And Anr VERSUS Sunita Rameshwar Ambore And Ors ... … Adv. A. S. Shelke, Advocate for Applicant ….. CORAM : S. G. CHAPALGAONKAR, J. Dated : 15TH APRIL, 2025 PER COURT :- CIVIL APPLICATION NO. 748 OF 2025 1. Heard Mr. Shelke, learned Advocate appearing for the applicants. 2. Applicants seek to condone the delay of 103 days caused in filing appeal. 3. Perused the application and reasons as stated therein. 2025:BHC-AUG:11073 2 169-ca-748-2025 Apparently, the delay is caused on account of administrative exigencies, it is not intentional. In result, Application is allowed in terms of prayer clause ‘B’ and disposed of. CIVIL APPLICATION NO. 749 OF 2025 1. Mr. Shelke, submits that the entire amount is deposited with the Commissioner for Employees Compensation. 2. In that view of the matter, keeping liberty to the applicants to file an application for withdrawal of amount, the Civil Application stands allowed in terms of prayer clause ‘C’ and disposed of. ( S. G. CHAPALGAONKAR, J. ) Rushikesh/2025