2025 DAILYLAW 65433 (KAR)

BASAVARAJ S/O SHANKAR KHOTH v. KARNATAKA POWER TRANSMISSION CORPORATION LIMITED

WP/100820/2021 · 2025-12-01

M Nagaprasanna

body2025

Judgment text

Extracted from the PDF above. The PDF is authoritative.

- 1 - HC-KAR NC: 2025:KHC-D:16817 WP No. 100820 of 2021 IN THE HIGH COURT OF KARNATAKA, AT DHARWAD DATED THIS THE 1ST DAY OF DECEMBER, 2025 BEFORE THE HON'BLE MR. JUSTICE M.NAGAPRASANNA WRIT PETITION NO. 100820 OF 2021 (GM-RES) BETWEEN: BASAVARAJ S/O SHANKAR KHOTH AGE 62 YEARS, OCC AGRICULTURE, R/O BENNADI, TQ NIPPANI, DIST BELAGAVI-591215. …PETITIONER (BY SRI. K.L. PATIL AND S. A SONDUR, ADVOCATE) AND: 1. KARNATAKA POWER TRANSMISSION CORPORATION LIMITED, REPRESENTED BY ITS MANAGING DIRECTOR, 38 CUBBON ROAD, 1ST FLOOR, SHIVAJI NAGAR, BENGALURU, KARNATAKA-560001. 2. M/S. SPENCER SYSTEMS BLOCK NO.AO-202, UMED S.NO.143, LAGAD MALA, SINHGAD ROAD, DHAYARI, PUNE 411041, MAHARASHTRA. 3. THE DEPUTY COMMISSIONER BELAGAVI DISTRICT, BELAGAVI-590001. …RESPONDENTS (BY SRI. B.S. KAMATI, ADVOCATE FOR R1; SRI. T. HANUMAREDDY, AGA FOR R3) Digitally signed by RAKESH S HARIHAR Location: High Court of Karnataka, Dharwad Bench, Dharwad - 2 - HC-KAR NC: 2025:KHC-D:16817 WP No. 100820 of 2021 THIS WRIT PETITION IS FILED UNDER ARTICLES 226 AND 227 OF THE CONSTITUTION OF INDIA PRAYING TO ISSUE WRIT OF MANDAMUS OR ORDER OR ANY OTHER APPROPRIATE WRIT OR DIRECTION TO THE RESPONDENT NO.1 AND 2 TO LAY THE TRANSMISSION LINE OR INSTALLING THE TOWERS IN OR NEAR THE LAND OF THE PETITIONER BEARING SY.NO.SURVEY NO.328/2A SITUATED AT BENNADI VILLAGE IN NIPPANI TALUK AFTER FOLLOWING THE PROVISIONS OF THE ELECTRICITY ACT 2003 AND INDIAN TELEGRAPH ACT 1885. THIS WRIT PETITION, COMING ON FOR ORDERS THIS DAY, ORDER WAS MADE THEREIN AS UNDER: ORAL ORDER (PER: THE HON'BLE MR. JUSTICE M.NAGAPRASANNA) 1. This Court on 09.03.2021 had passed the following order: “Sri. B.S.Kamate, learned standing counsel accepts notice for the respondent No.1. Issue emergent notice to respondent No.2. Learned High Court Government Pleader accepts notice for respondent No.3. Installation of transmission line and tower on petitioner’s land bearing Sy.No.328/2A shall be strictly in accordance with the provisions of the Indian Telegraph Act, 1885. List this matter on 23.03.2021.” 2. The Learned counsel for the respondent submits that the installation has been carried out in terms of the interim order so granted and the project is also complete. Therefore the - 3 - HC-KAR NC: 2025:KHC-D:16817 WP No. 100820 of 2021 petitioner shall avail of such remedy as is available in law for claiming compensation as the towers are said to be laid down in accordance with law. 3. The learned counsel for the respondent now submits the compensation is also paid to the petitioner. 4. In the light of the above, the petition stands disposed reserving liberty to seek revival of the subject petition in the event the submissions of the respondent would not be corrected. Ordered accordingly. Sd/- (M.NAGAPRASANNA) JUDGE RHR/-CT:ANB List No.: 2 Sl No.: 14