IN THE HIGH COURT OF JUDICATURE AT PATNA Civil Writ Jurisdiction Case No.12305 of 2023 ====================================================== Amber Infra Project Pvt. Ltd. having its registered office at Miscott, District Motihari, Bihar through its authorized Signatory Sushil Kumar Jha, Male, aged about 59 years, son of Trea Nath Jha, Resident of Village Badharwa Siwan, P.S. Dhaka, District East Champaran, Bihar. ... ... Petitioner/s Versus
1. The State of Bihar through the Additional Chief Secretary, Road Construction Department, Government of Bihar, Patna.
2. The Managing Director, Bihar Rajya Pool Nirman Nigam Ltd. Patna, Bihar.
3. The Senior Project Engineer, Bihar Rajya Pool Nirman Nigam Ltd. Works Division, Sitamarhi, District Sitamarhi.
4. The Deputy Engineer, North Bihar Circle, Bihar Rajya Pool Nirman Nigam Ltd. Patna Bihar.
5. The Executive Engineer, Road Construction Department, Road Division, Sitamarhi, District Sitamarhi, Bihar. ... ... Respondent/s ====================================================== Appearance : For the Petitioner/s : Mr.Prabhat Ranjan, Adv. For the Respondent/s : Mr.S. D. Yadav ( AAG 9 ) ======================================================
CORAM: HONOURABLE MR. JUSTICE A. ABHISHEK REDDY ORAL ORDER 4 23-01-2025
Learned counsel appearing on behalf of the petitioner seeks permission to withdraw the present writ petition.
2. Permission is granted.
3. Accordingly, the present writ petition stands dismissed as withdrawn.
Bhardwaj/- (A. Abhishek Reddy , J) U