937 1/2 IN THE HIGH COURT OF JUDICATURE AT BOMBAY NAGPUR BENCH, NAGPUR.
WRIT PETITION NO.893 OF 2025 YOGESHWAR S/O CHINDHUJI GANAR AND ANOTHER VS SUPERINTENDING ENGINEER, MAHA. AIRPORT DEVELOPMENT AUTHORITY LTD., NAGPUR AND ANR ______________________________________________________________________________ Office Notes, Office Memoranda of Coram, Appearances, Court's orders of directions Court's or Judge's order and Registrar's orders. Ms Rai, Advocate for the petitioner/s Mr. G.A. Kunte, Advocate for the respondent No.1 Mr. D.P. Thakre, Addl. G.P. for the respondent No.2/State ------------------------------- CORAM : ANIL S. KILOR AND R
AJNISH R. VYAS
, JJ.
DATE : 25.11.2025
1. Heard.
2. In the present petition, a prayer is made to direct the respondents to take decision on the application under Section 28-A of the Land Acquisition Act, 1894, submitted by the petitioners on 27.10.2022 and till date no decision has been taken on the same.
3. A prayer is innocuous and therefore, we are of the opinion that this petition can be disposed of with direction to the respondent No.2 to take decision on such application.
4. Accordingly, we dispose of the petition with direction to the respondent No.2 to take decision on the application under Section 28-A of the Land Acquisition Act, 1894 nd.thawre 2025:BHC-NAG:12885-DB
937 2/2 submitted on 27.10.2022, within eight weeks from today.
5. The learned counsel for the petitioners undertakes to furnish a copy of this order before the concerned authority within a period of one week from today.
(RAJNISH R. VYAS, J.) (ANIL S. KILOR, J.) nd.thawre