2025 DAILYLAW 60213 (KAR)

ASHOK S/O BHARAMAPPA BULLAPUR v. UNION OF INDIA

WP/102275/2024 · 2025-07-11

Pradeep Singh Yerur

Civil Appealbody2025

Judgment text

Extracted from the PDF above. The PDF is authoritative.

- 1 - HC-KAR NC: 2025:KHC-D:8668 WP No. 101870 of 2024 C/W.WP.Nos.100224, 102161 & 102275 of 2024. IN THE HIGH COURT OF KARNATAKA, DHARWAD BENCH DATED THIS THE 11TH DAY OF JULY, 2025 BEFORE THE HON'BLE MR. JUSTICE PRADEEP SINGH YERUR WRIT PETITION NO. 101870 OF 2024 (GM-RES) C/W WRIT PETITION NO. 100224 OF 2024 WRIT PETITION NO. 102161 OF 2024 WRIT PETITION NO. 102275 OF 2024 IN WRIT PETITION NO. 101870 OF 2024 BETWEEN: 1. GANESH S/O. NARAYANAPPA SALUNKE, AGED About: 50 YEARS, OCC: AGRICULTURE, R/O: RATTIHALLI VILLAGE, TQ: HIREKERUR, DIST: HAVERI – 581 116. 2. NARAYANAPPA S/O. DURGOJ SALUNKE, AGED ABOUT: 78 YEARS, OCC: AGRICULTURE, R/O: RATTIHALLI VILLAGE, TQ: HIREKERUR, DIST: HAVERI – 581 116. 3. MANJUNATH S/O. NARAYANAPPA SALUNKE, AGED ABOUT: 51 YEARS, OCC: AGRICULTURE, R/O. RATTIHALLI VILLAGE, TQ: HIREKERUR, DIST: HAVERI – 581 116. …PETITIONERS (BY SRI. M.R. HIREMATHAD & SRI. PRAKASH R. BADIGER, ADVOCATES) AND: 1. UNION OF INDIA, R/BY PRINCIPAL SECRETARY, VIJAYALAKSHMI M KANKUPPI Location: HIGH COURT OF KARNATAKA DHARWAD BENCH - 2 - HC-KAR NC: 2025:KHC-D:8668 WP No. 101870 of 2024 C/W.WP.Nos.100224, 102161 & 102275 of 2024. MINISTRY OF RAILWAY, NEW DELHI – 110 001. 2. THE GENERAL MANAGER, SOUTH WESTERN RAILWAY, GADAG ROAD, KESHWAPUR, HUBBALLI – 580 020. 3. KARNATAKA INDUSTRIAL DEVELOPMENT AUTHORITY, NO.49, 4 AND 5TH FLOOR, EAST WING, KANIJA BHAVAN, RACE CORSE ROAD, BANGALORE – 560 003. 4. KARNATAKA INDUSTRIAL DEVELOPMENT AUTHORITY, SPECIAL LAND ACQUISITION OFFICER, BUILDING NO.C.A.(1-B) GROUND FLOOR, KARUR INDUSTRIAL AREA, P.B. ROAD, DAVANAGERI – 577 006. 5. THE DEPUTY COMMISSIONER, HAVERI – 581 110. 6. THE TAHASHILDAR, RATTIHALLI, HAVERI – 581 116. …RESPONDENTS (BY SRI. MRUTYUNJAY S. HALLIKERI, ADVOCATE FOR R1 & R2; SMT. SHARMILA M. PATIL, ADVOCATE FOR R3 & R4; SRI. S.V. MAGADUM, AGA FOR R5 & R6) THIS WRIT PETITION IS FILED UNDER ARTICLES 226 AND 227 OF THE CONSTITUTION OF INDIA PRAYING TO ISSUE I. SEEKING A WRIT OF CERTIORARI ORDER DATED 06/11/2023 PASSED BY THE RESPONDENT NO.5 BEARING DC.HAV-15022(11/12/2023-HAV-LAQ VIDE ANNEXURE-D. II. ISSUE A WRIT, ORDER OR DIRECTION IN THE NATURE OF MANDAMUS DIRECTING TO RESPONDENTS RESURVEY AND - 3 - HC-KAR NC: 2025:KHC-D:8668 WP No. 101870 of 2024 C/W.WP.Nos.100224, 102161 & 102275 of 2024. CHANGE THE PROPOSED RAILWAY LINE AT RATTIHLLI, YALIWAL(SIDDAPUR) AND DODDAGUBBI VILLAGE. III. ISSUE A WRIT, ORDER OR DIRECTION, DIRECTING THE RESPONDENTS NO.2 TO 6 NOT TO DISPOSSESS THE PETITIONERS OF THE PETITION FROM THEIR LAND/PLOT/HOUSE. IV. GRANT SUCH OTHER RELIEFS AS DEEMED FIT BY THIS HON’BLE COURT IN THE CIRCUMSTANCES OF THE CASE, IN THE INTEREST OF JUSTICE AND EQUITY. IN WRIT PETITION NO. 100224 OF 2024 BETWEEN: 1. NAGANAGOUDA S/O. SHIVANAGOUDA PATIL, AGED ABOUT 67 YEARS, OCC: AGRICULTURE, R/O. RATTIHALLI VILLAGE, TQ: HIREKERUR, DIST: HAVERI – 581 116. 2. PRABHU S/O. RAVANAPPA MUDIVEERANNAVAR, AGED ABOUT 56 YEARS, OCC: AGRICULTURE, R/O. RATTIHALLI VILLAGE, TQ: HIREKERUR, DIST: HAVERI – 581 116. 3. BASANAGOUDA S/O.KAREGOUDA GHANTEPPAGOUDAR, AGED ABOUT 57 YEARS, OCC: AGRICULTURE, R/O. RATTIHALLI VILLAGE, TQ: HIREKERUR, DIST: HAVERI – 581 116. 4. DEVARAJ S/O. HALAPPA SURYAVAMSHI, AGED ABOUT 38 YEARS, OCC: AGRICULTURE, R/O. RATTIHALLI VILLAGE, TQ: HIREKERUR, DIST: HAVERI – 581 116. - 4 - HC-KAR NC: 2025:KHC-D:8668 WP No. 101870 of 2024 C/W.WP.Nos.100224, 102161 & 102275 of 2024. 5. UJANEPPA S/O. NAGAPPA DYAVAKKALAVAR, AGED ABOUT 39 YEARS, OCC: AGRICULTURE, R/O. RATTIHALLI VILLAGE, TQ: HIREKERUR, DIST: HAVERI – 581 116. 6. NAGAPPA S/O. GURANAGOUDA HOSALLI, AGED ABOUT 46 YEARS, OCC: AGRICULTURE, R/O. CHIKKA MATTUR VILLAGE, HIREKERUR TALUK, HAVERI DISTRICT – 581 109. 7. SMT. GIRIJAMMA W/O. BASAVARAJAPPA KAYAKAD, AGED ABOUT 62 YEARS, OCC: AGRICULTURE, R/O. RATTIHALLI VILLAGE, TQ: HIREKERUR, DIST: HAVERI – 581 116. 8. RUDRESH S/O. BEERAPPA HOLAJOGI, AGED ABOUT 39 YEARS, OCC: AGRICULTURE, R/O. RATTIHALLI VILLAGE, TQ: HIREKERUR, DIST: HAVERI – 581 116. 9. RAJU S/O. M. VEERAPPA MALAGOUDAR, AGE: 45, OCC: AGRICULTURE, R/O. RATTIHALLI VILLAGE, TQ: HIREKERUR, DIST: HAVERI – 581 116. 10. MAHADEVGOUDA S. PATIL, AGE: 59, OCC: AGRICULTURE, R/O. RATTIHALLI VILLAGE, TQ: HIREKERUR, DIST: HAVERI – 581 116. …PETITIONERS (BY SRI. M.R. HIREMATHAD & SRI. PRAKASH BADIGER, ADVOCATES) AND: 1. UNION OF INDIA, R/BY PRINCIPAL SECRETARY, MINISTRY OF RAILWAY, NEW DELHI – 110 001. 2. THE GENERAL MANAGER, SOUTH WESTERN RAILWAY, - 5 - HC-KAR NC: 2025:KHC-D:8668 WP No. 101870 of 2024 C/W.WP.Nos.100224, 102161 & 102275 of 2024. GADAG ROAD, KESHWAPUR, HUBBALLI – 580 020. 3. KARNATAKA INDUSTRIAL DEVELOPMENT AUTHORITY, NO.49, 4 AND 5TH FLOOR, EAST WING, KANIJA BHAVAN, RACE COURSE ROAD, BANGALORE – 560 003. 4. KARNATAKA INDUSTRIAL DEVELOPMENT AUTHORITY, SPECIAL LAND ACQUISITION OFFICE, BUILDING NO. C. A(1-B), GROUND FLOOR, KARUR INDUSTRIAL AREA, P.B. ROAD, DAVANGERI – 577 006. 5. THE DEPUTY COMMISSIONER, HAVERI DISTRICT, HAVERI – 581 110. 6. THE TAHASHILDAR, RATTIHALLI, DIST: HAVERI – 581 116. …RESPONDENTS (BY SRI. MRUTYUNJAY S. HALIKERI, ADVOCATE FOR R1 AND R2; SMT. SHARMILA M. PATIL, ADVOCATE FOR R3 & R4; SRI. SHARAD V. MAGADUM, AGA FOR R5 & R6) THIS WRIT PETITION IS FILED UNDER ARTICLES 226 AND 227 OF THE CONSTITUTION OF INDIA PRAYING TO I. SEEKING A WRIT OF CERTIORARI ORDER BEARING NO. DC-HAV-15022(11/12/2023-HAV-LAQ DATED 06/11/2023 PASSED BY THE RESPONDENT NO.5 VIDE ANNEXURE-D PERTAINING TO PETITIONER LAND ONLY. II. ISSUE A WRIT, ORDER OR DIRECTION IN THE NATURE OF MANDAMUS DIRECT TO RESPONDENTS NO.2 TO 4 RESURVEY AND CHANGE THE PROPOSED RAILWAY LINE AT RATTIHLLI, YALIWAL (SIDDAPUR) AND DODDAGUBBI VILLAGE. - 6 - HC-KAR NC: 2025:KHC-D:8668 WP No. 101870 of 2024 C/W.WP.Nos.100224, 102161 & 102275 of 2024. III. ISSUE A WRIT, ORDER OR DIRECTION, DIRECTING THE RESPONDENTS NO.2 TO 6 NOT TO DISPOSSESS THE PETITIONERS OF THE PETITION FROM THEIR LAND/PLOT/HOUSE. IV. GRANT SUCH OTHER RELIEFS AS DEEMED FIR BY THIS HON’BLE COURT IN THE CIRCUMSTANCES OF THE CASE, IN THE INTEREST OF JUSTICE AND EQUITY. IN WRIT PETITION NO. 102161 OF 2024 BETWEEN: JAGADISH S/O. SHEKAPPA EKKEGUNDI, AGE: 32 YEARS, OCC: AGRICULTURE, R/O: TADAKANHALLI VILLAGE, TQ: HIREKERUR, DIST: HAVERI – 581 116, HAVERI – 581 110. …PETITIONER (BY SRI. M.R. HIREMATHAD & SRI. PRAKASH R. BADIGER, ADVOCATES) AND: 1. UNION OF INDIA, R/BY PRINCIPAL SECRETARY, MINISTRY OF RAILWAY, NEW DELHI – 110 001. 2. THE GENERAL MANAGER, SOUTH WESTERN RAILWAY, GADAG ROAD, KESHWAPUR, HUBBALLI – 580 020, DIST: DHARWAD. 3. KARNATAKA INDUSTRIAL DEVELOPMENT AUTHORITY, R/BY CHIEF EXECUTIVE OFFICER, NO.49, 4 AND 5TH FLOOR, EAST WING, KANIJA BHAVAN, RACE CORSE ROAD, BANGALORE – 560 003. - 7 - HC-KAR NC: 2025:KHC-D:8668 WP No. 101870 of 2024 C/W.WP.Nos.100224, 102161 & 102275 of 2024. 4. KARNATAKA INDUSTRIAL DEVELOPMENT AUTHORITY, SPECIAL LAND ACQUISITION OFFICER, BUILDING NO.C.A(1-B), GROUND FLOOR, KARUR INDUSTRIAL AREA, P.B. ROAD, DAVANAGERI – 577 006. 5. THE DEPUTY COMMISSIONER, HAVERI – 581 110. 6. THE TAHASHILDAR, RATTIHALLI, HAVERI – 581 116. …RESPONDENTS (BY SRI. MRUTYUNJAY S. HALLIKERI, ADVOCATE FOR R1& R2; SMT. SHARMILA M. PATIL, ADVOCATE FOR R3 AND R4; SRI. SHARAD V. MAGADUM, AGA FOR R5 & R6) THIS WRIT PETITION IS FILED UNDER ARTICLES 226 AND 227 OF THE CONSTITUTION OF INDIA PRAYING TO I. SEEKING A WRIT OF CERTIORARI ORDER BEARING NO. DC-HAV-15022(11/112/2023- HAV-LAQ DATED 06/11/2023 PASSED BY THE RESPONDENT NO. 5 VIDE ANNEXURE-D INSOFAR PETITIONER LAND/PROPERTY BEARING NO.1/94 OF RATTIHALLI GRAM PANCHAYAT. II. ISSUE A WRIT, ORDER OR DIRECTION IN THE NATURE OF MANDAMUS DIRECTING TO RESPONDENTS NO. 2 TO 4 RESURVEY AND CHANGE THE PROPOSED RAILWAY LINE AT RATTIHLLI, YALIWAL (SIDDAPUR) AND DODDAGUBBI VILLAGE. III. ISSUE A WRIT, ORDER OR DIRECTION, DIRECTING THE RESPONDENTS NO. 2 TO 6 NOT TO DISPOSSESS THE PETITIONERS OF THE PETITION FROM THEIR LAND/PLOT/HOUSE. - 8 - HC-KAR NC: 2025:KHC-D:8668 WP No. 101870 of 2024 C/W.WP.Nos.100224, 102161 & 102275 of 2024. IV. GRANT SUCH OTHER RELIEFS AS DEEMED FIT BY THIS HON’BLE COURT IN THE CIRCUMSTANCES OF THE CASE, IN THE INTEREST OF JUSTICE AND EQUITY. IN WRIT PETITION NO. 102275 OF 2024 BETWEEN: 1. ASHOK S/O. BHARAMAPPA BULLAPUR, AGE: 39 YEARS, OCC: AGRICULTURE, R/O: KODAMAGGI MASURU VILLAGE, TQ: HIREKERUR, DIST: HAVERI – 581 210. 2. BELAKERAPPA S/O. HANUMANTAPPA GUNDAGATTI, AGED ABOUT 54 YEARS, OCC: AGRICULTURE, R/O: KODAMAGGI MASURU VILLAGE, TQ: HIREKERUR, DIST: HAVERI – 581 210. 3. KRISHNAPPA S/O. LATE DEVAPPA BANKARPUR, AGED ABOUT: 67 YEARS, OCC: AGRICULTURE, R/O: KODAMAGGI MASURU VILLAGE, TQ: HIREKERUR, DIST: HAVERI – 581 210. 4. RAMACHANDRAPPA S/O. HANUMNTHAPPA JADAV, AGED ABOUT: 62 YEARS, OCC: AGRICULTURE, R/O: KODAMAGGI MASURU VILLAGE, TQ: HIREKERUR, DIST: HAVERI – 581 210. 5. NAJEER SAB S/O. MUNAF SAB SIDDAPUR, AGED ABOUT: 48 YEARS, OCC: AGRICULTURE, R/O: KODAMAGGI MASURU VILLAGE, TQ: HIREKERUR, DIST: HAVERI – 581 210. 6. SAJJANSHETTAR VIRUPAPAKSHAPPA S/O. SHIVARUDRAPPA, AGED ABOUT: 82 YEARS, OCC: AGRICULTURE, R/O: MASURU VILLAGE, TQ: HIREKERUR, DIST: HAVERI – 581 210. - 9 - HC-KAR NC: 2025:KHC-D:8668 WP No. 101870 of 2024 C/W.WP.Nos.100224, 102161 & 102275 of 2024. 7. BEERAPPA S/O. HALAPPA GUNDAGATTI, AGED ABOUT: 39 YEARS, OCC: AGRICULTURE, R/O: KODAMAGGI MASURU VILLAGE, TQ: HIREKERUR, DIST: HAVERI – 581 210. 8. SALIHA S/O. ANWAR SAB, AGED ABOUT: 44 YEARS, OCC: AGRICULTURE, R/O: KODAMAGGI MASURU VILLAGE, JANATA PLOT, TQ: HIREKERUR, DIST: HAVERI – 581 210. 9. KRISHNAJI RAV DHULOJI KARATA, AGED ABOUT: 76 YEARS, OCC: AGRICULTURE, R/O: KODAMAGGI MASURU VILLAGE, TQ: HIREKERUR, DIST: HAVERI – 581 210. 10. TALAVAR THIRUKAPPA S/O. PAKKIRAPPA (TALAVAR), AGED ABOUT: 53 YEARS, OCC: AGRICULTURE, R/O: KODAMAGGI MASURU VILLAGE, TQ: HIREKERUR, DIST: HAVERI – 581 210. …PETITIONERS (BY SRI. M R HIREMATHAD & SRI. PRAKASH BADIGER, ADVOCATES) AND: 1. UNION OF INDIA, R/BY PRINCIPAL SECRETARY, MINISTRY OF RAILWAY, NEW DELHI – 110 001. 2. THE GENERAL MANAGER, SOUTH WESTERN RAILWAY, GADAG ROAD, KESHWAPUR, HUBBALLI – 580 020, DIST: DHARWAD. 3. KARNATAKA INDUSTRIAL DEVELOPMENT AUTHORITY, R/BY CEO, NO.49, 4 AND 5TH FLOOR, EAST WING, KANIJA BHAVAN, RACE CORSE ROAD, BANGALORE – 560 003. - 10 - HC-KAR NC: 2025:KHC-D:8668 WP No. 101870 of 2024 C/W.WP.Nos.100224, 102161 & 102275 of 2024. 4. KARNATAKA INDUSTRIAL DEVELOPMENT AUTHORITY, R/BY SLA OFFICER, SPECIAL LAND ACQUISITION OFFICER, BUILDING NO.C.A(1-B), GROUND FLOOR, KARUR INDUSTRIAL AREA, P.B. ROAD, DAVANAGERI – 577 006. 5. THE DEPUTY COMMISSIONER, HAVERI – 581 110. 6. THE TAHASHILDAR, RATTIHALLI, HAVERI – 581 116. …RESPONDENTS (BY SRI. MRUTYUNJAY S. HALLIKERI, ADVOCATE FOR R1& R2; SMT. SHARMILA M. PATIL, ADVOCATE FOR R3 AND R4; SRI. SHARAD V. MAGADUM, AGA FOR R5 & R6) THIS WP IS FILED UNDER ARTICLES 226 AND 227 OF THE CONSTITUTION OF INDIA PRAYING TO A) SEEKING A WRIT OF CERTIORARI ORDER BEARING NO. DC-HAV- (11/12/2023-HAV-LAQ DATED 06/11/2023 PASSED BY THE RESPONDENT NO.5 VIDE ANNEXURE-D. B) ISSUE A WRIT, ORDER OR DIRECTION IN THE NATURE OF MANDAMUS DIRECT TO RESPONDENTS NO.2 TO 4 RESURVEY AND CHANGE THE PROPOSED RAILWAY LINE AT RATTIHLLI, YALIWAL (SIDDAPUR) AND DODDAGUBBI VILLAGE. C) ISSUE A WRIT, ORDER OR DIRECTION, DIRECTING THE RESPONDENTS NO.2 TO 6 NOT TO DISPOSSESS THE PETITIONERS OF THE PETITION FROM THEIR LAND/PLOT/HOUSE. D) GRANT SUCH OTHER RELIEFS AS DEEMED FIT BY THIS HON’BLE COURT IN THE CIRCUMSTANCES OF THE CASE, IN THE INTEREST OF JUSTICE AND EQUITY. - 11 - HC-KAR NC: 2025:KHC-D:8668 WP No. 101870 of 2024 C/W.WP.Nos.100224, 102161 & 102275 of 2024. THESE WRIT PETITIONS COMING ON FOR PRELIMINARY HEARING IN ‘B’ GROUP THIS DAY, ORDER WAS MADE THEREIN AS UNDER: ORAL ORDER (PER: THE HON'BLE MR. JUSTICE PRADEEP SINGH YERUR) 1. Heard learned counsel for the petitioners and learned AGA as well as the learned counsel for the respondents. 2. Petitioners are before this Court seeking to quash the impugned order passed by the 5th respondent dated 06.11.2023 and for a direction to re-survey or change the alignment of the proposed new railway line between Shivamogga-Shikaripur-Ranebennur railway line. 3. The Central Government Railway Department approved new railway line project between Shivamogga- Shikaripur-Ranebennur at an estimated cost of ₹832.45 crores on 50:50 per share between the State Government and Central Government. The railway line proposed to start from Shivamogga-via-Shikaripur-Ranebennur. The respondents No.2 to 4 accordingly appointed the Survey Officers and other required persons for survey and - 12 - HC-KAR NC: 2025:KHC-D:8668 WP No. 101870 of 2024 C/W.WP.Nos.100224, 102161 & 102275 of 2024. mapping of route of the railway line. According to the petitioners, the railway line starts from Shivamogga to Shikaripur and to end at Ranebennuru. The same passes through Survey Nos.105/B, 106A, 106/2, 204 and 89 of the Rattihalli village of Haveri District. Said survey numbers are converted to non-agriculture lands and some petitioners have already constructed their houses. Hence, the petitioners made a representation to respondents No.5 and 6 requesting the proposed line passing through between village and between residential houses is affecting the villagers and sought for re-survey of the proposed railway project. 4. It is further contented by the learned counsel for the petitioners that respondents no.5 and 6 forwarded the same to respondent no.4 and recommended to change the railway line. Respondent No.4 has requested respondent no.6, which was forwarded to respondent no.4 to recommend the change of the railway line. - 13 - HC-KAR NC: 2025:KHC-D:8668 WP No. 101870 of 2024 C/W.WP.Nos.100224, 102161 & 102275 of 2024. 5. The petitioners have also made a representation to respondent no.2 and requested to change the modification of the proposed railway line, which was not considered by the respondents. Hence, the petitioners filed a Writ Petition No.105848/2022, whereby this Court disposed of the same, directing the respondents to consider the representation of the petitioners and the respondents No.1 and 2 to take suitable actions and pass appropriate orders. Thereafter, the respondent/Railway Department considered the representation and issued an endorsement dated 20.03.2023. It is the grievance of the petitioners that the respondent/Railways and the KIADB intending to change the entire station platform and may change from its original plan and the alignment which was initially prepared. Thereby affecting the individual rights of the petitioners and the property rights of the petitioners, thereby violating their rights to property including Article 300A of the Constitution of India to enjoy property of the petitioners. - 14 - HC-KAR NC: 2025:KHC-D:8668 WP No. 101870 of 2024 C/W.WP.Nos.100224, 102161 & 102275 of 2024. 6. Learned counsel for the petitioners further contends that he does not have any objection in original allignment, which was made by the Railway Department to continue and the acquisition process to be continued in accordance with law by following the due process of law, rather than changing the alignment plan and the construction of the platforms being shifted time and again to suit certain influential persons. Hence, the present petition by the petitioners. 7. Learned counsel Sri Mrutyunjay S. Hallikeri appearing for the respondent/Railway Department submits that the Railway Board had sanctioned the reconnaissance Engineering survey for connecting existing Shivamogga station to existing Ranebennur station via Shikaripura in the year 2012. Based on the survey order made, alignments were made duly indicating techno economic analysis for each alignment which are drawn and based on the techno economic analysis the present alignment has been finalized and submitted to the Railway Board in the - 15 - HC-KAR NC: 2025:KHC-D:8668 WP No. 101870 of 2024 C/W.WP.Nos.100224, 102161 & 102275 of 2024. year 2017 at the cost of ₹956.48 crores. He further submits that the alignment of the project has been finalized keeping in mind all the parameters particularly interest of the local public as the project is of public importance. However, he contends that the final location survey has been sanctioned by the Railway Board in the year 2017 and the new line has been sanctioned by the Railway Board in the year 2019 for ₹994.47 crores. Accordingly, the Government of Karnataka issued Government Order No.IDD 31 NSW 2017 dated 22.08.2019 for taking up the subject project on cost sharing basis with a cost of ₹956.10 crore and land cost of at ₹244.73 crores. This being the state of affairs, there were certain objections raised and the petitioners had approached this Court and obtained an order. Based on the order passed by this Court, the issue was re- examined, duly taken up for consideration and all aspects suggested by the petitioners were considered including shifting of alignment by 200 meters towards north of Rattihalli Town was examined and it was found that that - 16 - HC-KAR NC: 2025:KHC-D:8668 WP No. 101870 of 2024 C/W.WP.Nos.100224, 102161 & 102275 of 2024. there will be substantial increase in the cost of railway project to the tune of nearly ₹20 crore as there will be necessary connections at either ends, which necessitates sharper degree of curvature and extra road on bridge. This will invite permanent speed restrictions of 90 km/h as against the designed speed of 160 km/h for the present alignment. 8. It is further contended that permanent speed restriction will further get compounded due to the proximity of canal waterway due to seepage of water into the proposed formation of the alignment, thereby affecting the safety. 9. Learned counsel further contends that before considering these aspects Railway Department has conducted due diligence considering all the parameters the techno-economic feasibility, speed potential as well as proximity to the users with well-connected approach of the existing villages for the alignment of the railway line to the particular area. Therefore, after analyzing all these aspects - 17 - HC-KAR NC: 2025:KHC-D:8668 WP No. 101870 of 2024 C/W.WP.Nos.100224, 102161 & 102275 of 2024. which was decided that there was no possibility of shifting the alignment based on the techno-economic feasibility as suggested by the petitioners. The learned counsel further contends that in case of even shifting assuming for the sake of argument, one or the other persons land will be acquired for formation of the railway line and either the petitioners or the other landowners will be affected. Therefore, on the basis of techno-economic feasibility and due diligence, the railway alignment line has been finalized, which would be considered by the KIADB for acquisition and the acquisition process would be conducted in accordance to the Act, Rules and due process of law would be followed by providing suitable notice and principles of natural justice would be followed. 10. Learned counsel for respondents no.3 and 4 concurs with the arguments put forth by learned counsel for the Railway Department and she contends that the present petition filed by the petitioners is vexatious without there being any interest for the general public. It - 18 - HC-KAR NC: 2025:KHC-D:8668 WP No. 101870 of 2024 C/W.WP.Nos.100224, 102161 & 102275 of 2024. is only for the benefit of petitioners rather than the public cause. He further contends that the alignment so made by the Railway Department to the railway line is far from the school and it does not affect the school in any manner as contended by the petitioners. So also the requirement of the railway line is on the basis of no profit and no loss and it is required for the public purpose and public at large. Therefore, when the public purpose is the larger interest, the private individual interest would yield to the larger public interest in such situations where railway lines are sought to be laid for the development of the neighbouring areas, villages and public at large. On these grounds, he seeks to dismiss the petition of the petitioners. 11. I have heard learned counsel for the petitioners and learned counsel for the respondents. The petitioners were before this Court in the earlier round of litigation, whereby this court directed the respondents to consider the representation of the petitioners and pass suitable orders in accordance with law. On the basis of the said - 19 - HC-KAR NC: 2025:KHC-D:8668 WP No. 101870 of 2024 C/W.WP.Nos.100224, 102161 & 102275 of 2024. order passed by this court, the respondents have reconsidered whether there could be any possibility or feasibility of changing the railway line alignment from the one which was already initiated by the Railway Department after conducting the necessary economic analysis and alternative alignments. The request of the petitioners for changing the line and shifting it was reiterated that there was no possibility of shifting the alignment as suggested by the petitioners as it would cause both hardship and inconvenience to the public at large and also the financial expenses which will be huge. On these grounds, the respondents have decided to proceed further with the alignment to lay the line as was decided by the Railway Department. 12. It is the grievance of the petitioners that the respondents are conducting the survey interfering the petitioner's property without there being any acquisition and without following the due process of law, without providing any notice and violating the principles of natural - 20 - HC-KAR NC: 2025:KHC-D:8668 WP No. 101870 of 2024 C/W.WP.Nos.100224, 102161 & 102275 of 2024. justice. The learned counsel for the respondents submits that they would acquire the property by following due process of law and proceed further for acquisition by initiating necessary process inconsonance with Section 28 of the Karnataka Industrial Area Development Board Act following the process or procedure laid down under the Act by notifying concerned persons including receiving and others interested giving scope for filing objections to the petitioners and thereafter proceed further with the acquisition process in accordance with law. 13. In WP.102275/2024, preliminary notification has already been issued under Section 28(1) of the KIADB Act, the further process has been stopped in view of the orders passed by this Court, thereafter counsel submit that they would follow due process of law by notifying, thereafter and proceed further in the acquisition proceedings. - 21 - HC-KAR NC: 2025:KHC-D:8668 WP No. 101870 of 2024 C/W.WP.Nos.100224, 102161 & 102275 of 2024. 14. Therefore, under the circumstances, I do not find any good or cogent reason to interfere in this petition to show indulgence to these petitioners on the issuance of impugned order. Accordingly, I pass the following: ORDER (i) Petition is dismissed. (ii) However, it is made clear that the respondents shall follow the due process of law while acquiring the properties for laying down the railway line, consider the objections, if any, of the petitioners and also provide a hearing if required to the petitioners while passing the orders, including survey and acquisition and the issuance of notification both preliminary and final. Sd/- (PRADEEP SINGH YERUR) JUDGE KGK/CKK CT-MCK List No.: 1 Sl No.: 78