THE EXECUTIVE ENGINEER v. THE SPECIAL LAND ACQUISITION OFFICER
MFA/102828/2024 · 2025-01-22
Hanchate Sanjeevkumar
body2025
DailyLaw.ai
[ 2025 DAILYLAW 5932 (KAR) · dailylaw.ai ]
DailyLaw.ai
[ 2025 DAILYLAW 5932 (KAR) · dailylaw.ai ]
Judgment text
Extracted from the PDF above. The PDF is authoritative.
IN THE HIGH COURT OF KARNATAKA, DHARWAD BENCH DATED THIS THE 22ND DAY OF JANUARY 2025
BEFORE
THE HON'BLE MR. JUSTICE HANCHATE SANJEEVKUMAR
MISCELLANEOUS FIRST APPEAL NO. 102828 OF 2024 (LAC)
BETWEEN:
1 .
THE EXECUTIVE ENGINEER SINGATALUR LIFT IRRIGATION PROJECT, K.I.C.LTD., MUNDARAGI TQ. MUNDARAGI, DIST.GADAG ... APPELLANT
(By SRI. SHIVARAJ.C.BELLAKKI, ADVOCATE)
AND: 1 .
THE SPECIAL LAND ACQUISITION OFFICER SINGATALUR LIFT IRRIGATION SCHEME, HUVINAHADAGALI.
2 .
ODISOMATH KALLAYYA S/O MAHALINGAYYA AGE. MAJOR, R/O.HIREVADATTI TQ. MUNDARAGI, DIST. GADAG
3 .
GAVISIDDAYYA S/O MAHALINGAYYA AGE: MAJOR, R/O.HIREVADATTI/ HAROGERI TQ. MUNDARAGI, DIST. GADAG.
... RESPONDENTS * * * * * This Miscellaneous First Appeal filed Under Section 54(1) of Land Acquisition Act, against the Judgment and Award dated 8TH DAY OF APRIL 2024 passed in LAC No.273/2019 on the file of The Additional District and Sessions Judge Gadag.
2 This appeal coming on for orders this day, the Hon’ble Court passed the following;
O R D E R
Four weeks time is granted to comply with the office objections, failing which, the appeal stands dismissed without reference to the Court. SD/- JUDGE
//COPY// As per the endorsement made in the order sheet dated 04.03.2025, the Advocate for appellant has not complied with the office objections. Hence, this MFA No. 102828 of 2024 stands dismissed as per the Court order dated
22.01.2025.
BY ORDER OF THE COURT
SD/-
ASSISTANT REGISTRAR.
T By: vg C By: sms