IN THE HIGH COURT AT CALCUTTA [CIRCUIT BENCH AT PORT BLAIR] ***
WPA/191/2025
Akabea Insfrastructures Pvt. Ltd.
Vs
The Chief Engineer and others
Mrs. Anjili Nag, Sr. Adv.
Mr. Adarsh Ilango
… for the petitioners
Mr.Shatadru Chakraborty, Sr. Adv. Mr. Dibesh Dwivedi … for the respondent Nos. 1&2 April 9, 2025 [AKB] Item No.14
1. The learned counsel Mr. Dibesh Dwivedi has submitted that the relevant tender process has been cancelled due the administrative reasons. He has submitted one communication between the concerned parties.
2. Let the same be kept with the record.
3. In view of the above, the instant writ application has become infructuous and is accordingly disposed of.
(Apurba Sinha Ray, J.)