Extracted from the PDF above. The PDF is authoritative.
APHC010585752025
IN THE HIGH COURT OF ANDHRA PRADESH AT AMARAVATI (Special Original Jurisdiction) [3457] TUESDAY, THE FOURTH DAY OF NOVEMBER TWO THOUSAND AND TWENTY FIVE PRESENT THE HONOURABLE SRI JUSTICE HARINATH.N WRIT PETITION NO: 30376/2025 Between: Nulaka Ramaiah ...PETITIONER AND The State Of Andhra Pradesh and Others ...RESPONDENT(S) Counsel for the Petitioner:
1. Sri DASARI S V V S V PRASAD Counsel for the Respondent(S):
1. Ld. GP MUNCIPAL ADMN AND URBAN DEV AP
2. Ld. GP FOR FINANCE PLANNING
3. Sri Gudapati Lakshmi Narayana, Ld. Standing Counsel for R.3 The Court made the following:
-2- W.P. No.30376 OF 2025 Date of order: 04.11.2025
THE HON’BLE SRI JUSTICE HARINATH.N WRIT PETITION No.30376 OF 2025 ORDER:
1. This writ petition is filed aggrieved by the action of the respondents for non-payment of the bills for the works undertaken by the petitioner. 2. Heard the submissions of the learned counsel for the petitioner, the learned Government Pleader for Municipal Administration and Urban Development, the learned Assistant Government Pleader for Finance and Planning, and the learned Standing Counsel for the respondent- Corporation. 3. The learned counsel for the petitioner submits that the 3rd respondent entrusted the work to the petitioner under agreement No.431/2023-2024 and supplementary agreement No.724 of 2023-2024 dt.08.03.2024. The details of the work is, the removal of silt in major drains at various places in Dharmavaram Municipality. 4. The learned counsel further submits that the petitioner duly executed the work to the satisfaction of the 3rd respondent. It is further submitted that after execution of the works, the progress of the work was recorded in the M book. Later, the petitioner submitted a final bill. The authorities of the 3rd respondent, after deducting necessary charges and other expenses, approved the final bill for a sum of Rs.12,99,157/-, but so far no payment has been made to the petitioner. -3- W.P. No.30376 OF 2025 Date of order: 04.11.2025
5. The learned standing counsel for the 3rd respondent, on oral instructions, submits that the work undertaken by the petitioner was completed to the satisfaction of the authorities of the 3rd respondent. However, on account of lack of funds, the payment could not be made to the petitioner and that payment would be made in due course. 6.
Considering the submissions that the work completed by the petitioner is not in dispute and on account of the lack of funds, the payment for the work undertaken by the petitioner could not be released, there shall be a direction to respondents 2 and 3 to verify and release the payments due payable to the petitioner within a period of four weeks. 7. With the above direction, the writ petition is disposed of. No costs. 8. Pending miscellaneous petitions, if any, shall stand closed. ___________________ JUSTICE HARINATH.N BV