Neutral Citation No. - 2025:AHC:79514 Court No. - 50 Case :- WRIT - B No. - 1746 of 2025 Petitioner :- Bhagawan Das Respondent :- State Of U P And 12 Others Counsel for Petitioner :- Prabhakar Dubey Counsel for Respondent :- C.S.C. Hon'ble Chandra Kumar Rai,J. 1.Learned counsel for the petitioner is permitted to make necessary correction in the prayer of the writ petition during course of the day. 2. Heard Mr. Prabhakar Dubey, learned counsel for the petitioner and Mr. Hari Mohan Srivastava, learned Standing Counsel for the State-respondents. 3.The instant writ petition has been filed for the following relief:-
"(i). Issue a writ, order or direction in the nature of mandamus directing the respondent no.2 to consider the grounds of petitioner and decide the revision No.444 computerized Case No.202254054700001430 Bhagwan Das Versus Awadhraj and others on merit in some stipulated period."
4. Learned counsel for the petitioner submitted that chak revision No. 444 of 2024 computerized case No.202254054700001430 filed by the petitioner is pending before respondent No.2/ Deputy Director of Consolidation, Maharajganj since 2022. He submitted that direction should be issued for expeditious disposal of the pending chak revision within time bound period and till the disposal of revision the effect and operation of the order passed by appellate court should be stayed. He further submitted that transfer application filed by private respondent No.4 to transfer the
pending chak revision has been dismissed. 5. Mr. Hari Mohan Srivastava, learned Additional Chief Standing Counsel for the State-respondents submitted that chak revision filed by petitioner is pending since 2022 before Deputy Director of Consolidation, as such prayer for grant of interim order in this matter should not be allowed. 6. I have considered the arguments advanced by the learned counsel for the parties and perused the record. 7. There is no dispute about the fact that chak revision filed by petitioner is pending before respondent No.2/Deputy Director of Consolidation, Maharajganj since 2022. 8. Considering the entire facts and circumstances of the case, the writ petition is finally disposed of directing the respondent No.2/Deputy Director of Consolidation, Maharajganj to decide the aforementioned chak revision expeditiously preferably within a period of two months from the date of production of certified copy of this order before him after giving opportunity of hearing to the parties concerned and without granting unnecessary adjournments to either of the parties.
Order Date :- 14.5.2025 PS* Digitally signed by :- PRITI SHARMA High Court of Judicature at Allahabad