8536.23ca (1) IN THE HIGH COURT OF JUDICATURE AT BOMBAY BENCH AT AURANGABAD
938-4 CIVIL APPLICATION NO. 8536 OF 2023 IN FAST/516/2023 THE EXECUTIVE ENGINEER JALGAON MEDIUM PROJECT DIVISION JALGAON VERSUS GAJANAN EKNATH MAHAJAN & OTHERS …. Mr A. D. Pawar, Advocate for applicant Mr A. H. Koralkar, Advocate for respondent Nos.1(i) to 1(v) Mr S. K. Shirse, A.G.P. for respondent No.2 WITH CIVIL APPLICATION NO. 8538 OF 2023 IN FAST/530/2023 THE EXECUTIVE ENGINEER JALGAON MEDIUM PROJECT DIVISION JALGAON VERSUS NARAYAN BUDHA MALI DIED, THROUGH LRS RAJENDRA NARAYAN MAHAJAN & OTHERS …. Mr A. D. Pawar, Advocate for applicant Mr A. H. Koralkar, Advocate for respondent Nos.1(i) to 1(v) Mr S. K. Shirse, A.G.P. for respondent No.2 WITH CIVIL APPLICATION NO. 8540 OF 2023 IN FAST/528/2023 THE EXECUTIVE ENGINEER JALGAON MEDIUM PROJECT DIVISION JALGAON VERSUS LAXMAN BUDHA BORASE & ANR. …. Mr A. D. Pawar, Advocate for applicant Mr A. H. Koralkar, Advocate for respondent Nos.1 Mr S. K. Shirse, A.G.P. for respondent No.2
8536.23ca (2)
CORAM : PRAFULLA S. KHUBALKAR, J.
DATE : 4th July, 2025 PER COURT:
1.
Learned counsel for the applicant/appellant submits that in accordance with the order dated 20/03/2025, the appellant has deposited the entire amount within the time granted.
2. In view of this, the interim relief granted by order dated 20/03/2025 to operate during the pendency of the first appeals.
3. The civil applications are disposed of.
(PRAFULLA S. KHUBALKAR, J.) sjk