Neutral Citation No. - 2025:AHC:64944-DB Court No. - 21 Case :- WRIT - C No. - 12841 of 2025 Petitioner :- Sudarshan Kumar And 3 Others Respondent :- State Of U.P. And 2 Others Counsel for Petitioner :- Vikrant Rana Counsel for Respondent :- C.S.C.,Shiv Prakash Gupta Hon'ble Manoj Kumar Gupta,J. Hon'ble Anish Kumar Gupta,J.
1. The writ petition filed by the petitioners bearing No.37459 of 2023 was considered by a Co-ordinate Bench and the following order was passed on 19.03.2024:
"1. In view of the statement made by learned counsel for the respondents that the
order under challenge in writ has been withdrawn, we find that no further grievance survives to the petitioners, as of now.
2. Writ petition, accordingly, stands consigned to records."
2. During pendency of the said writ petition, the Vice-Chairman, Meerut Development Authority, Meerut passed an order dated 24.02.2024 and the order passed on 26.09.2023, which was subject matter of challenge in the writ petition, was withdrawn and it was directed that the allotment of the plot in favour of the petitioners would stand restored in terms of the decision of the State Government and that the petitioners would be provided the calculation in respect of the remaining amount, as per the guideline of the State Government issued in the year
1999. The petitioners, in terms of the said development, withdrew the writ petition, as evident from order dated 19.03.2024. On 14.02.2025, the Vice-Chairman, Meerut Development Authority, Meerut passed another order in which he reiterated the stand that the petitioners' allotment would stand restored and the rates applicable at the time of cancellation would apply and also that the petitioners would be intimated about the cost of shifting of the electricity line passing through their land.
3. The sole grievance of the petitioners is that so far they have not been communicated with the amount, which has to be deposited by the petitioners, as per
order of the Vice-Chairman, Meerut Development Authority, Meerut dated
14.02.2025.
4. Shri Shiv Prakash Gupta, learned counsel appearing on behalf of Meerut Development Authority, Meerut states that computation of the amount payable by the petitioners, based on the rates applicable in the year 2014, would be supplied to
the petitioners within two weeks from today.
5. Having regard to the said statement, the writ petition stands disposed of by providing that the Development Authority would provide the computation sheet to the petitioners based on the rates applicable in the year 2014 in terms of the order of the Vice-Chairman dated 14.02.2025 and decision of the State Government within two weeks from today.
6. The site plan of the plot shall also be provided to the petitioners alongwith the computation sheet. (Anish Kumar Gupta, J.) (Manoj Kumar Gupta, J.)
Order Date :- 28.4.2025 Ankit. Digitally signed by :- ANKIT VISHWAKARMA High Court of Judicature at Allahabad