HIGH COURT OF ANDHRA PRADESH :: AMARAVATI
W.P.No.5426 OF 2025 PROCEEDING SHEET Sl. No. DATE ORDER OFFICE NOTE
04. 27.10.2025 JS,J:
I.A.No.2 of 2025
This application is filed by the 4th respondent by stating that the petitioner in W.P.No.5426 of 2025, has given an undertaking to the 4th respondent dated 27.06.2025 that the petitioner will not claim or charge any interest or compensation.
In view of the undertaking given by the petitioner in W.P.No.5426 of 2025, this application is ordered.
The respondents are directed to release the amount within four (04) weeks from the date of receipt of a copy of this Order.
________ JS,J SCH