HC-KAR NC: 2025:KHC:33097 WP No. 20306 of 2025 IN THE HIGH COURT OF KARNATAKA AT BENGALURU DATED THIS THE 23RD DAY OF AUGUST, 2025 BEFORE THE HON'BLE MR. JUSTICE R DEVDAS WRIT PETITION NO. 20306 OF 2025 (KLR-RR/SUR) BETWEEN:
VITTALA SALIAN AGED ABOUT 73 YEARS, S/O THAMMA NALKERA, R/AT NO.14, SUNITHA NIVASA, SHETTIBETTU NITTE VILLAGE, KARKALA TALUK, UDUPI DIST-574110 …PETITIONER (BY SRI. VISHWAS, ADVOCATE) AND:
1.
THE PRINCIPAL SECRETARY TO GOVERNMENT DEPARTMENT OF REVENUE M. S. BUILDING, DR.B.R.AMBEDKAR VEEDHI, BANGALORE-560009
2.
DEPUTY COMMISSIONER, UDUPI DISTRICT, RAJATADRI, MANIPAL, UDUPI-576104
3.
ASSISTANT COMMISSIONER, DEPARTMENT OF REVENUE, KUNDAPURA, UDUPI- 576201
4.
DEPUTY DIRECTOR OF LAND RECORDS UDUPI DISTRICT, RAJATADRI, Digitally signed by KAVYA R Location: High Court of Karnataka
- 2 -
HC-KAR NC: 2025:KHC:33097 WP No. 20306 of 2025 MANIPAL, UDUPI-576104
5. TASHILDAR KARKALA TALUK UDUPI DIST-574104
6.
ASSISTANT DIRECTOR OF LAND RECORDS KARKALA TALUK UDUPI DIST-574104 …RESPONDENTS (BY SRI. V. SESHU, HCGP)
THIS W.P.IS FILED UNDER ARTICLES 226 & 227 OF THE CONSTITUTION OF INDIA PRAYING TO DIRECT THE RESPONDENTS TO COMPLETE THE PHODI OF THE LAND MEASURING 0.24 CENTS IN S.NO. 635//1 OF NITTE VILLAGE, KARKALA TALUK, UDUPI DISTRICT, PURSUANT TO THE APPLICATION OF THE PETITIONER DTD. 24.10.2023 (ANNX-C).
THIS PETITION, COMING ON FOR FINAL HEARING, THIS DAY, ORDER WAS MADE THEREIN AS UNDER:
CORAM:
HON'BLE MR. JUSTICE R DEVDAS ORAL ORDER Learned HCGP takes notice for all the respondents.
2. The grievance of the petitioner is that although he filed an application online on 24.10.2023 seeking phodi and durasth of the lands in question, no action has been taken by respondents Nos.5 and 6.
- 3 -
HC-KAR NC: 2025:KHC:33097 WP No. 20306 of 2025
3.
Learned Counsel submits that in terms of the provisions of the Act, exercise of phodi and Durasth should be undertaken and completed within a stipulated time.
4. Consequently, the writ petition stands
disposed of with a specific direction to respondent Nos.5 and 6 to proceed to conduct phodi and Durasth and complete the process as expeditiously as possible and at any rate within a period of two months from the date of receipt of a copy of this order. Ordered accordingly. Sd/- (R DEVDAS) JUDGE YN. List No.: 1 Sl No.: 20