1 17-WP-9499-2024.doc IN THE HIGH COURT OF JUDICATURE AT BOMBAY CIVIL APPELLATE JURISDICTION
WRIT PETITION NO. 9499 OF 2024 Mandeshi Prabodhankar Magaswargiya Sahakari Soot Girni Maryadit ...Petitioner Versus The State of Maharashtra and Ors. ...Respondents **** Mr. Pramod Patil a/w Shyamsunder Solanke, Advocates for the Petitioner. Mr. P.G. Sawant, Assistant Government Pleader for the Respondent Nos. 1 to 3/State. Mr. Omkar Nagvekar, Advocate for the Respondent No.4. **** CORAM :
A.S.CHANDURKAR AND M.M. SATHAYE, JJ.
DATE :
25th APRIL 2025 P.C. :
1. Pursuant to the order dated 17.04. 2025, the learned Assistant Government pleader on instructions submits that on 21.04.2025 a meeting of the Steering Committee was held, wherein a decision was taken with regard to the project report concerning the Petitioner society. It was decided to have the said proposal revised after which final approval in the matter could be granted. It is further submitted that time of three months would be required to do the needful.
2. The minutes of the meeting dated 21.04.2025 are taken on record and marked ‘A’ as identification. Accepting the statement made on institutions, it is directed that within a period of three months from the receipt of this order, the entire process in the matter of grant of approval to the revised project report for the Petitioner society be undertaken. Sneha Chavan 1/2 SNEHA NITIN CHAVAN Digitally signed by SNEHA NITIN CHAVAN Date: 2025.04.25 17:33:01 +0530
2 17-WP-9499-2024.doc
3. With the aforesaid directions, Writ Petition is disposed of.