Howden Air and Gas India Private Limited, v. BGR Boilers Private Limited,
A/1558/2025 · 2025-03-25
Abdul Quddhose
Transfer Petitionbody2025
DailyLaw.ai
[ 2025 DAILYLAW 40585 (MAD) · dailylaw.ai ]
DailyLaw.ai
[ 2025 DAILYLAW 40585 (MAD) · dailylaw.ai ]
Judgment text
Extracted from the PDF above. The PDF is authoritative.
Appln. No.1558 of 2025 THE HIGH COURT OF JUDICATURE AT MADRAS DATED: 25.03.2025 CORAM:
THE HON'BLE MR. JUSTICE ABDUL QUDDHOSE Appln. No.1558 of 2025 Howden Air and Gas India Private Ltd., Rep. by its Authorised Signatory Sambit Dash ... Applicant Vs BGR Boilers Private Ltd., Rep. by its Managing Director ... Respondent For Applicant : Mr. Aditya Mukerjee - - - - - The learned counsel for the respondent has stated no objection for allowing this application.
2. This application has been filed under Section 29A of the Arbitration and Conciliation Act, 1996 seeking extension of time for the Arbitral Tribunal to pronounce the Arbitral Award for a further period of 12 months w.e.f. 14.03.2025 until 13.03.2026. 1/3 https://www.mhc.tn.gov.in/judis
Appln. No.1558 of 2025
3. This Court is satisfied with the reasons contained in the affidavit filed in support of this application as sufficient cause has been shown by the applicant for seeking extension of time as prayed for. Accordingly, this application is allowed as prayed for and the mandate of the Arbitral Tribunal to pronounce the Arbitral Award is extended for a further period of 12 months w.e.f. 14.03.2025 until 13.03.2026. 25.03.2025 vsi2 2/3 https://www.mhc.tn.gov.in/judis
Appln. No.1558 of 2025 ABDUL QUDDHOSE, J. vsi2 Appln. No.1558 of 2025 25.03.2025 3/3 https://www.mhc.tn.gov.in/judis