2025 DAILYLAW 38347 (HP)

ROOP LAL v. THE HPSEBL AND OTHERS

CWP/17674/2025 · 2025-11-14

Jyotsna Rewal Dua

body2025

Judgment text

Extracted from the PDF above. The PDF is authoritative.

IN THE HIGH COURT OF HIMACHAL PRADESH, SHIMLA CWP No. 17674 of 2025 a/w CWP Nos. 17676, 17678 & 17680 of 2025 Decided on: 14.11.2025 1. CWP No. 17674 of 2025 Roop Lal …Petitioner Versus H.P. State Electricity Board Ltd. & another .…Respondents. 2. CWP No. 17676 of 2025 Roshan Lal …Petitioner Versus H.P. State Electricity Board Ltd. & another .…Respondents. 3. CWP No. 17678 of 2025 Sher Singh …Petitioner Versus H.P. State Electricity Board Ltd. & another .…Respondents. 4. CWP No. 17680 of 2025 Man Singh …Petitioner Versus H.P. State Electricity Board Ltd. & another .…Respondents. ………………………………………………………………………………. Coram Ms. Justice Jyotsna Rewal Dua, Judge. Whether approved for reporting?1 For the petitioner(s): Mr. Bonit Prakash, Advocate. For the respondents: Mr. Virender Singh, Advocate for respondents in CWP No.17674/ 2025, 17678/2025 & 17680/2025. Mr. Deepak Sharma, Advocate for respondents in CWP No.17676/ 2025. Jyotsna Rewal Dua , J Notice. Mr. Virender Singh & Mr. Deepak Sharma, learned counsel, appear and waive service of notice on behalf of the respective respondents in all the matters. 1 Whether reporters of the local papers may be allowed to see the judgment? yes 2 2. These writ petitions have been filed for grant of almost identical relief, which has been reproduced from CWP No.17674 of 2025 :- “i) That the respondents may be ordered to grant work charge status to the petitioner from the date he completed 8 years service with all benefits incidental thereof.” 3. Learned counsel for the petitioners submits that the cases of the petitioners and the reliefs prayed for by them are covered under decision rendered in The Himachal Pradesh State Electricity Board Ltd. & Anr. Vs. Nanak Chand & Ors.2 In the aforesaid case, the respondent-Board had contended that the case in hand was distinct from State of Himachal Pradesh and Ors. Vs. Surajmani & Anr.3 as in the respondent-Board, work charge establishment was abolished in 1986, therefore, the directions given in Surajmani3 cannot be applied in the respondent-Board. The Hon’ble Apex Court rejected the contentions and held that the judgment in Surajmani3 squarely applies and the directions issued therein shall applicable mutatis mutandis to Himachal Pradesh State Electricity Board as well. Relevant portion of the decision reads as under:- “2. In counter to the said argument, in the counter affidavit, Standing orders of the Himachal Pradesh State Electricity Board Industrial Establishment framed in exercise of the provisions of the Factories Act, 1948 have been shown whereby Clause 5(b) makes it clear that the Board shall have the following class of workmen in different establishments. Clause 5(b) indicate work establishment 2 SLP(C) Nos. 10719-10720/2025, decided on 16.04.2025. 3 Civil Appeal No.1595/2025, decided on 06.02.2025. 3 having work charged work commission. The said fact has not been controverted except to say in the affidavit that they have abolished the work charged establishment in the year1986. In the list of date also, it is stated that the work charge establishment has been revised in 1987. 3. Considering all these aspects, there is no reason to take a different view from the case of Surajmani (supra). The operative portion of the judgment of Surajmani is reproduced for ready reference : "10. For the cumulative reasons aforestated, we are of the considered view that the dicta laid down by this Court vide order dated 22.07.2019 in Ashwani Kumar's (Supra) case which is based on the judgment of Mool Raj Upadhyaya (Supra) holds the field and would also be applicable to the Respondents herein who had approached the Tribunal or the High Court seeking similar relief. As such, the Respondents shall be entitled for grant of 'work-charged' status from the date of completion of 8 years of service. However, we hold that the relief in the present appeals will be limited to notional benefits as explained in paragraph 3 and 4 of Ashwani Kumar's (Supra) case in Civil Appeal No(s). 5753 of 2019 and the present appeals stand disposed of accordingly with no order as to costs. 11. We also make it explicitly clear that the State in its endeavour of implementing the orders of the Tribunal, High Court or this Court, if having paid the amounts in excess, would be at liberty to take such steps as it deems fit without insisting for one time recovery. 12. It is further underscored that this judgment would necessarily be a judgment in rem and the State shall hence forth not take recourse to employing personnel as daily wagers but shall make appointments only in accordance with law, as enumerated in the case of Secretary, State Karnataka Vs. Uma Devi [ (2006) 4 SCC 1]." 4. In our view, the judgment of Surajmani squarely applies and the said directions shall be applicable mutatis mutandis in the case of Himachal Pradesh State Electricity Board also.” 4 4. In view of above, respondents are directed to consider the respective cases of the petitioners for grant of reliefs prayed for by them in light of decision rendered in Nanak Chand2, within a period six weeks from today. The decision so taken be communicated to the petitioners. The writ petitions stand disposed of in the above terms, so also the pending miscellaneous application(s), if any. Jyotsna Rewal Dua Judge 14th November, 2025(yogesh)