$~30 * IN THE HIGH COURT OF DELHI AT NEW DELHI + W.P.(C) 5946/2025, CM APPL. 27095/2025 & CM APPL. 27096/2025 SH UTTAM SINGH .....Petitioner Through: Mr. Vikas Sood and Mr. Harsh Vikram Trivedi, Advs. (Through VC) versus MUNICIPAL CORPORATION OF DELHI AND ORS. .....Respondents Through: Mr. Rakesh Malhotra, Mr. Bharat Malhotra and Ms. Smritika Kesri, Avds. For MCD CORAM:
HON'BLE MS. JUSTICE MINI PUSHKARNA O R D E R % 28.10.2025
1. The present petition has been filed seeking directions to respondent no. 1, to take action against the unauthorized construction being carried out by respondent no.3 on the third floor along with terrace at property bearing No. B-1/418, B-Block, Janakpuri, New Delhi-110058. 2. A Status Report dated 08th August, 2025, has been filed on behalf of Municipal Corporation of Delhi (“MCD”), relevant portions of which, read as under: This is a digitally signed order. The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 29/10/2025 at 12:37:45
This is a digitally signed order. The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 29/10/2025 at 12:37:45
This is a digitally signed order. The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 29/10/2025 at 12:37:45
This is a digitally signed order. The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 29/10/2025 at 12:37:45
3. Perusal of the aforesaid Status Report shows that part demolition action has already been taken by the MCD on 28th August, 2024 and 08th May, 2025. 4. Accordingly, it is directed that in case there is further unauthorized construction existing in the property in question, action shall be taken against the same, in accordance with law. 5. It is further directed that no unauthorized construction shall be allowed to take place in the property in question. 6.
In case any party is aggrieved by any action or non-action on the part of the MCD, their right to seek remedies in accordance with law, is reserved. 7. With the aforesaid directions, the present writ petition, along with the pending applications, is accordingly, disposed of. MINI PUSHKARNA, J OCTOBER 28, 2025/KR This is a digitally signed order. The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 29/10/2025 at 12:37:45