PUNJAB STATE ELECTRICITY BOARD v. ASHOK KUMAR (READMIS.)
RSA/1462/1998 · 2025-07-04
Harkesh Manuja
body2025
DailyLaw.ai
[ 2025 DAILYLAW 35972 (PNJ) · dailylaw.ai ]
DailyLaw.ai
[ 2025 DAILYLAW 35972 (PNJ) · dailylaw.ai ]
Judgment text
Extracted from the PDF above. The PDF is authoritative.
125
IN THE HIGH PUNJAB STATE ELECTRICITY BOARD
ASHOK KUMAR
CORAM: HON'BLE MR. JUSTICE
Present: Mr. H.S. Baidwan,
None for the respon HARKESH MANUJA Present appeal has been filed while laying challenge to
judgment and decree Court i.e. Addl. District Judge, Gurdaspur whereby, an appeal preferred at the instance of dated 30.01.1993 passed by the Court of learned Sub Class, Pathankot came to be dismissed.
2.
Very briefly, it may be pointed out here that the plaintiff happened to be situated at Railway Road, Pathankot having connections b
3.
As per the case pleaded by inspection was carried out by question on 11.08.1988 connection No.840 Rs.21,898/- was imposed upon the respondent electricity besides imposition of Rs.550/ towards RCO fees. In addition, penalty of Rs. on account of excess load. CS which was installed at the first floor of the building in question, a penalty of Rs.22,671 was imposed upon the alleging theft
IN THE HIGH COURT OF PUNJAB AND HARYANA AT CHANDIGARH Date of Decision:
PUNJAB STATE ELECTRICITY BOARD
Versus ASHOK KUMAR
HON'BLE MR. JUSTICE HARKESH MANUJA Mr. H.S. Baidwan, Advocate for the None for the respondent. **** HARKESH MANUJA, J. (ORAL)
Present appeal has been filed while laying challenge to
judgment and decree dated 22.12.1997 passed by the First Appellate Court i.e. Addl. District Judge, Gurdaspur whereby, an appeal preferred at the instance of appellant-defendant against dated 30.01.1993 passed by the Court of learned Sub lass, Pathankot came to be dismissed. Very briefly, it may be pointed out here that the happened to be co-owner of a building known as at Railway Road, Pathankot having connections bearing Nos.840-CS, 793-CS and 850 As per the case pleaded by inspection was carried out by its Flying Squad of the premises in on 11.08.1988, wherein, it was connection No.840-CS was tampered with and accordingly, penalty of was imposed upon the respondent electricity besides imposition of Rs.550/- as co RCO fees. In addition, penalty of Rs. count of excess load. With respect to meter connection No.793 CS which was installed at the first floor of the building in question, a penalty of Rs.22,671 was imposed upon the theft of electricity on account of
COURT OF PUNJAB AND HARYANA AT CHANDIGARH RSA-1462-1998 Date of Decision: July 04, 2025
........Appellant
........Respondent HARKESH MANUJA Advocate for the appellant.
Present appeal has been filed while laying challenge to the dated 22.12.1997 passed by the First Appellate Court i.e. Addl. District Judge, Gurdaspur whereby, an appeal preferred against the judgment and decree dated 30.01.1993 passed by the Court of learned Sub-Judge First Very briefly, it may be pointed out here that the respondent- owner of a building known as ‘Tourist Hotel’ at Railway Road, Pathankot having three electricity meter CS and 850-CS. As per the case pleaded by the appellant-defendant, an Flying Squad of the premises in rein, it was found that seal of meter pered with and accordingly, penalty of was imposed upon the respondent-plaintiff towards theft of as cost of meter and Rs.50/- RCO fees. In addition, penalty of Rs.4250/- was also imposed ith respect to meter connection No.793- CS which was installed at the first floor of the building in question, a penalty of Rs.22,671 was imposed upon the respondent-plaintiff while of tampered seals. Further, 1998 July 04, 2025
the dated 22.12.1997 passed by the First Appellate Court i.e. Addl. District Judge, Gurdaspur whereby, an appeal preferred
judgment and decree Judge First - ‘Tourist Hotel’ electricity meter n Flying Squad of the premises in that seal of meter pered with and accordingly, penalty of plaintiff towards theft of - was also imposed - CS which was installed at the first floor of the building in question, a while Further, TEJWINDER SINGH 2025.07.17 23:43 I agree to specified portions of this document
RSA-1462-1998
-2-
with respect to the electricity meter bearing No.850-CS which was installed on the ground floor of the premises in question, Rs.2270/- was imposed upon respondent-plaintiff towards excess load charges.
4.
The respondent-plaintiff filed a suit for declaration as well as mandatory injunction, assailed the aforementioned penalties imposed by the appellant-defendant and prayed for restoration of electricity connections to the original positions. It may be noticed here that admittedly, with respect to electricity meter connection No.850-CS, the excess load penalty amounting to Rs.2270/- was deposited by the respondent-plaintiff there and then on 11.08.1988 and the said electricity connection was restored in his favour.
5.
The trial Court vide judgment and decree dated 30.01.1993
decreed the suit in favour of respondent-plaintiff while recording that since the electricity meters relating to connection Nos.840-CS and 793- CS were never sent by the appellant-defendant to the M&T Lab and in the absence thereof, no finding could be recorded with respect to the tampering of those meters, therefore, the demand raised on account of theft of electricity was illegal. However, with respect to penalty amounting to Rs.4250/- relating to electricity connection No.840-CS towards excess load, the same was upheld in favour of appellant- defendant besides upholding of the demand of Rs.550/- towards cost of meter and Rs.50/- as RCO fee. Aggrieved of the judgment and decree passed by the trial Court, the appellant-defendant filed first appeal, however, the same came to be dismissed vide judgment and decree dated 22.12.1997, hence the present appeal.
6.
It may be pointed out here that in terms of the judgments and decrees passed by the two Courts below, a sum of Rs.4250/- imposed as penalty towards excess load upon electricity connection meter No.840-CS, Rs.550/- as cost of meter and Rs.50/- as RCO fees stood deposited by the respondent-plaintiff with the appellant- defendant.
TEJWINDER SINGH 2025.07.17 23:43 I agree to specified portions of this document
RSA-1462-1998
-3-
7.
Impugning the judgments and decrees passed by the Courts below, learned counsel for the appellant vehemently submits that the inspection by the Field Officer/Flying Squad was conducted in the presence of respondent-plaintiff on 11.08.1988 and a report prepared at the spot was even signed by him. He also submits that the report regarding tampering of seals was prepared by the Flying Squad having inspected the electricity meters and accordingly, the penalty towards theft of electricity was imposed upon the respondent-plaintiff. It was further submitted that the Courts below failed to take into consideration the detailed evidence available on record and as such, the judgments and decrees passed by the Courts below were liable to be set aside.
8.
No one has chosen to appear on behalf of respondent.
9.
I have heard learned counsel for the appellant and gone through the paper-book. I am unable to find substance in the
submissions made by learned counsel for the appellant.
10.
Admittedly, the penalty imposed upon respondent-plaintiff towards excess load qua the two electricity meter connection Nos.840- CS and 793-CS stood paid to the appellant-defendant besides payment of Rs.550/- against cost of meter and Rs.50/- as RCO fees. Hence, the dispute only remained with respect to the imposition of penalty towards theft of electricity on account of alleged tampering of M&T seals in both meters by the respondent-plaintiff. In this regard, it may be pointed out here that a concurrent finding of fact has been recorded by both the Courts below while relying upon statement made by PW-1 Ashok Kumar, UDC, PSEB, Sub-Division Pathankot who categorically deposed that the meters relating to electricity connection Nos. 840-CS and 793-CS regarding which there were allegations of theft of electricity on account of tampering of M&T seals were never sent for testing to any approved Laboratory by the appellant-defendant. Thus, in the absence of both the aforementioned electricity meters ever been sent for testing to the M&T Lab so as to assess whether the seals were tampered with; no penalty towards theft of electricity could have been imposed upon the respondent-plaintiff by the appellant-defendant. Unless the electricity meters were sent and examined at Laboratory, no
TEJWINDER SINGH 2025.07.17 23:43 I agree to specified portions of this document
RSA-1462-1998
-4- conclusive evidence could be recorded about tampering followed by any automatic presumption about dishonest abstraction of electricity. Besides it, no other substantive independent evidence about the functioning or working of the two electricity meters been affected or recording incorrect consumption was not produced and therefore, the demand made by appellant-defendant on account of meter seals of the two electric connections been tampered with was wholly unjustified.
11.
Accordingly, in view of the detailed discussion made herein- above, finding no illegality or perversity with the concurrent findings of fact recorded by the Courts below, there being no overlooking of the material available on record, re-appreciation of pleadings and evidence being impermissible, the present appeal being devoid of merits is thus, dismissed.
12.
Pending application(s), if any, shall also stand disposed of.
04.07.2025
(HARKESH MANUJA) Tejwinder
JUDGE Whether speaking/reasoned Yes/No Whether Reportable Yes/No
TEJWINDER SINGH 2025.07.17 23:43 I agree to specified portions of this document