ARB-181-2025 (O&M) -1- 111+255 IN THE HIGH COURT OF PUNJAB AND HARYANA AT CHANDIGARH ARB-181-2025 (O&M) Date of decision: 28.07.2025 M/S GREEN GLOBAL ENERGY ...Petitioner(s) VERSUS G. R. INFRAPROJECTS LIMITED ...Respondent(s)
CORAM:
HON'BLE MR. JUSTICE JASGURPREET SINGH PURI Present:- Mr. D. K. Singal, Advocate for the petitioner. Mr. Amandeep Singh, Advocate and Mr. Anant Garg, Advocate for the respondent. **** JASGURPREET SINGH PURI, J. (Oral) CM-14552-CII-2025 Prayer in this application is for placing on record the settlement deed dated 23.07.2025 as Annexure P-27. For the reasons mentioned in the application, the same is allowed. The settlement deed dated 23.07.2025 as Annexure P-27 is taken on record, subject to all just exceptions. ARB-181-2025
1.
Learned counsel for the petitioner submitted that during the pendency of the present petition, the entire matter has been settled between the parties and it has been reduced in the form of writing and therefore, he does not wish to press the present petition and prays for withdrawal of the same.
CHETAN THAKUR 2025.07.29 14:17 I attest to the accuracy and authenticity of this order/judgment.
ARB-181-2025 (O&M) -2-
2.
Learned counsel for the respondent submitted that he has instructions to state that a written compromise has been entered into between the parties and the entire matter has been settled between the parties.
3. The aforesaid request made by the learned counsel for the petitioner is accepted.
4. Dismissed as withdrawn.
(JASGURPREET SINGH PURI) 28.07.2025 JUDGE Chetan Thakur Whether speaking/reasoned : Yes/No Whether reportable : Yes/No CHETAN THAKUR 2025.07.29 14:17 I attest to the accuracy and authenticity of this order/judgment.