THE EXECUTIVE ENGINEER, SINA KOLEGAON MAJOR, LIFT IRRIGATION PROJECT, AT PARANADA, OSMANABAD v. SURENDRA AMBADAS NARSALE AND ORS
CA/621/2025 · 2025-04-17
Shri S G Chapalgaonkar
body2025
DailyLaw.ai
[ 2025 DAILYLAW 32579 (BOM) · dailylaw.ai ]
DailyLaw.ai
[ 2025 DAILYLAW 32579 (BOM) · dailylaw.ai ]
Judgment text
Extracted from the PDF above. The PDF is authoritative.
(1) 68-ca-621-2025.odt IN THE HIGH COURT OF JUDICATURE AT BOMBAY BENCH AT AURANGABAD CIVIL APPLICATION NO. 621 OF 2025 IN FAST/32433/2024 THE EXECUTIVE ENGINEER, SINA KOLEGAON MAJOR, LIFT IRRIGATION PROJECT, AT PARANADA, OSMANABAD VERSUS SURENDRA AMBADAS NARSALE AND ORS ... Mrs. Snehal Prashant Kulkarni, Advocate for Applicant. Mr. S. S. Dande, AGP for Respondents-State. Mr. V. B. Deshmukh, Advocate for Respondent No.1. ...
CORAM : S. G. CHAPALGAONKAR, J.
DATED : 17th APRIL, 2025. P.C.:-
1. Heard learned Advocates appearing for respective parties.
2. By this application, applicant seeks to condone delay of 111 days caused in filing appeal against award passed by Reference Court.
3. Perused reasons as stated in application. The delay appears to have been caused on account of administrative exigency. The applicant has not derived any advantage by making such delay. Although respondents are served, contents of application are not controverted. Hence, sufficient cause is made out to condone delay. Hence, following order:
ORDER a. Civil Application is allowed. b. Delay of 111 days caused in filing appeal is hereby condoned. c. Appeal be registered subject to removal of office objections.
(S. G. CHAPALGAONKAR) JUDGE Devendra/April-2025 2025:BHC-AUG:11171