NC: 2025:KHC:5079 WP No. 21194 of 2024
IN THE HIGH COURT OF KARNATAKA AT BENGALURU DATED THIS THE 4TH DAY OF FEBRUARY, 2025 BEFORE THE HON'BLE MR JUSTICE S.G.PANDIT WRIT PETITION NO. 21194 OF 2024 (S-TR) BETWEEN:
SRI. NARAYANAPPA G R S/O LATE GADDE RANGAPPA, AGED ABOUT 59 YEARS 2 MONTHS, WORKING AS EXECUTIVE ENGINEER, KARNATAKA INDUSTRIAL AREAS DEVELOPMENT BOARD, ZONAL OFFICE, KARUR INDUSTRIAL AREA, DAVANGERE - 577006. …PETITIONER (BY SRI. VIJAYA KUMAR V. B., ADV.)
AND:
1.
THE STATE OF KARNATAKA REP. BY ITS PRINCIPAL SECRETARY, COMMERCE AND INDUSTRIES DEPARTMENT, VIKAS SOUDHA, BENGALURU - 560001.
2.
THE CHIEF EXECUTIVE OFFICER AND EXECUTIVE MEMBER KARNATAKA INDUSTRIAL AREAS DEVELOPMENT BOARD, KHANIJA BHAVAN BENGALURU - 560001.
3.
SRI G H SRIDHAR EXECUTIVE ENGINEER,
Digitally signed by MARIGANGAIAH PREMAKUMARI Location: HIGH COURT OF KARNATAKA
- 2 -
NC: 2025:KHC:5079 WP No. 21194 of 2024
KARNATAKA INDUSTRIAL AREAS DEVELOPMENT BOARD, ZONAL OFFICE, BALLARY, VIJAYANAGAR DISTRICT -583101. …RESPONDENTS (BY SRI. SHIVAPRABHU HIREMATH, AGA FOR R1 SRI B.B. PATIL, ADV. FOR R2 SRI L MAHESH, ADV. FOR R3)
THIS PETITION IS FILED UNDER ARTICLE 226 OF THE CONSTITUTION OF INDIA PRAYING TO CALL FOR RELEVANT RECORDS RELATING TO ISSUE OF IMPUGNED NOTIFICATION BEARING NO.CT 216 IAP (E) 2024 (BHAGA-3) DATED 31.07.2024 ISSUED BY R-1 VIDE ANNX-E AND AFTER PERUSAL SET ASIDE THE SAME IN SO FAR AS TRANSFER OF R-3 AND PETITIONER AT SI.NO.7 AND 8 ARE CONCERNED.
THIS PETITION, COMING ON FOR ORDERS, THIS DAY,
ORDER WAS MADE THEREIN AS UNDER:
CORAM: HON'BLE MR JUSTICE S.G.PANDIT
ORAL ORDER
The petitioner, working as Executive Engineer in the second respondent-Karnataka Industrial Area Development Board is before this Court, questioning Annexure-E Notification bearing No.CI 216 IAP(E) 2024 (bhaga-3) dated 31.07.2024 insofar as transfer and posting of respondent No.3 in his place on various grounds.
- 3 -
NC: 2025:KHC:5079 WP No. 21194 of 2024
2. This Court, by interim order dated 06.08.2024 stayed the operation and execution of impugned notification dated 31.07.2024 (Annexure-E).
3. Today, during the course of hearing, when the learned Additional Government Advocate was asked to answer as to how the transfer of the petitioner is effected when this Court had directed the Government to continue the petitioner at Davanagere till his retirement by order dated 03.04.2024 in W.P.No.2080/2024, the learned Additional Government Advocate on getting instructions by afternoon has filed an affidavit dated 04.02.2025 of the Principal Secretary to Government, Department of Commerce and Industries, enclosing a Notification dated 04.02.2025 wherein the impugned Notification dated 31.07.2024 insofar as petitioner is concerned is withdrawn.
4. In the affidavit of the Principal Secretary to Government, Department of Commerce and Industries it is stated that by over-sight and inadvertence, the name of
- 4 -
NC: 2025:KHC:5079 WP No. 21194 of 2024
the petitioner appeared in the impugned notification dated 31.07.2024 and he has rendered unconditional apology.
5. In view of withdrawal of the impugned notification dated 31.07.2024 insofar as petitioner and 3rd respondent is concerned, the grievance of the petitioner would no more survive for consideration. Accordingly, the writ petition stands disposed of.
Sd/- (S.G.PANDIT) JUDGE
MPK CT:bms List No.: 1 Sl No.: 5