APHC010445162025 IN THE HIGH COURT OF ANDHRA PRADESH AT AMARAVATI (Special Original Jurisdiction) TUESDAY, THE SECOND DAY OF SEPTEMBER TWO THOUSAND AND TWENTY FIVE PRESENT THE HONOURABLE SRI JUSTICE HARINATH.I^ WRIT PETITION NO: 23165 OF 2025 . Between: Sri Kommineni Sandeep Naidu, S/o. K Ravi Prakash Naidu, R/o. 25/688-D, T T D Road, Near TTD kalayana Mandapam Srinivasa Nagar, Nandyal, Nandyal District, AP -518501. ...Petitioner AND
1. The State of Andhra Pradesh, Rep by its Principal Secretary Department of Municipal Administration and Urban Development Secretariat Velagapudi, Amaravathi, Guntur District. 2. The State of Andhra Pradesh, Rep.by its Principal Secretary, Department of Finance and Planning Amaravathi, Guntur District. 3. The District Collector, Nandyal, Nandyal District. 4. The Nandyal Municipality, Represented by its Commissioner, Nandyal, Nandyal District. 5. The Municipal Engineer, Nandyal Municipality, Nandyal, Nandyal District. Secretariat, Velagapudi, ...Respondents Petition under Article 226 ofthe Constitution of India praying that in the circumstances stated in the affidavit filed therewith, the High Court may be pleased to issue an appropriate Writ Order or direction more particularly one^
/ in the nature of Writ of Mandamus declaring the action of the Respondents in withholding the payments of pending amount of Rs. 12,05,720/- (Twelve Lakh Five Thousand Seven Hundred and Twenty Rupees only) for the year 2023- 2024, even after finalizing the bills, payable to the petitioner in relation to the work Construction of Community Toilet at PV Nagar Area of Nandyal Municipality (4th call) as bad, illegal, arbitrary, improper, unjust and against the Article 21 of Constitution of India and consequently direct the Respondents to pay the amounts of Rs. 12,05,720/- (Twelve Lakh Five Thousand Seven Hundred and Twenty Rupees only) forthwith release the payments of above bill amount along with 12% interest. lA NO: 1 OF 2025 Petition under Section 151 CPC praying that in the circumstances stated in the affidavit filed in support of the petition, the High Court may be pleased to direct the respondents to release and pay the amounts of Rs. 12,05,720/- (Twelve Lakh Five Thousand Seven Hundred and Twenty Rupees only) release the payments of the bill amount along with 12% interest, pending disposal of the writ petition.
Counsel for the Petitioner: SRI THATHIREDDY ASHOK SRIVASTAVA Counsel for the Respondent No.3: GP FOR REVENUE _ Counsel for the Respondent No.1: GP FOR MUNCIPAL ADMN AND- URBAN DEV Counsel for the Respondent No.2: GP FOR FINANCE & PLANNING ^ Counsel for the Respondent Nos. 4 & 5: SRI G LAKSHMI NARAYANA (SC FOR MUNICIPALITIES) ^ The Court made the following order:
// APHC010445162025 IN THE HIGH COURT OF ANDHRA PRADESH ATAMARAVATI (Special Original Jurisdiction) [3457] TUESDAY,THE SECOND DAY OF SEPTEMBER TWO THOUSAND AND TWENTY FIVE PRESENT THE HONOURABLE SRI JUSTICE HARINATH.N WRIT PETITION NO: 23165/2025 Between: Kommineni Sandeep Naidu ...PETITIONER AND ...RESPONDENT(S) The State Of Andhra Pradesh and Others Counsel for the Petitioner:
1 .THATHiREDDY ASHOK SRiVASTAVA Counsel for the Respondent(S):
1.GP FOR REVENUE 2.GP MUNCIPAL ADMN AND URBAN DEV AP 3.GP FOR FINANCE PLANNING The Court made the following:
2 W.P. No.23165 OF 2025 Date of order:02.09.2025 THE HON’BLE SRI JUSTICE HARINATH.N WRIT PETITION No.23165 OF 2025
ORDER
1. The learned counsel for the petitioner submits that the petitioner has executed works as entrusted by the respondent corporation and submitted final bills. It is submitted that the final bill was also endorsed by the competent engineers and also recorded the progress of work and certified the work in the M-Book. It is submitted that, in all an amount of Rs. 12,05,720/- is due and payable by the respondents to the petitioner. The learned counsel further submits that the respondents also issued check measurement certificate and completion certificate to the petitioners. Though the work progress was recorded in the M-Book, no amounts have been forth coming.
2. Heard the submissions of the learned counsel for the petitioner, the learned Government Pleader for Municipal Administration & Urban Development, the learned standing counsel for the Corporation, the learned Assistant Government Pleader for Finance and Planning.
3. Considering the submissions, respondents 2 and 4 are hereby
directed to verify and release the payments due payable to the
3 W.P. No.23165 OF 2025 Date of order:02.09.2025 petitioner as expeditiously as possible preferably within four (04) weeks from the date of receipt of a copy of this order.
4. Accordingly, the writ petition is disposed of. No a period of costs.
5. Pending miscellaneous petitions, if any, shall stand closed.
Sd/- M. RAMESH BABU DEPUTY REGISTRAR //TRUE COPY// SECTION OFFICER To,
1. The Principal Secretary Department of Municipal Administration and Urban Development Secretariat Velagapudi, Amaravathi, Guntur District.
2. The Principal Secretary, Department of Finance and Planning Secretariat, Velagapudi, Amaravathi, Guntur District.
3. The District Collector, Nandyal, Nandyal District.
4. The Commissioner, Nandyal Municipality, Nandyal, Nandyal District.
5. The Municipal Engineer, Nandyal Municipality, Nandyal, Nandyal District.
6. One CC to Sri Thathireddy Ashok Srivastava, Advocate [OPUC]
7. One CC to Sri G Lakshmi Narayana (SC for Municipalities), Advocate [OPUC]
8. Two CCs to GP for Revenue, High Court of Andhra Pradesh [OUT]
9. Two CCs to GP for Muncipal Admn and Urban Dev, High Court of Andhra Pradesh [OUT]
10. Two CCs to GP for Finance & Planning, High Court of Andhra Pradesh [OUT]
11. Two CD Copies TF
HIGH COURT DATED:02/09/2025
ORDER WP NO. 23165 OF 2025 AND^ I 18 SFP J025 mj ^ . Current Section .
DISPOSING OF THE W.P., WITHOUT COSTS