Research › Search › Judgment

High Court of Jharkhand · body

2025 DAILYLAW 28814 (JHR)

M/S VIJAI ELECTRICALS LTD THRO ITS AUTHORIZED SIGNATORY MR. P SRINIVASA RAO (GM-MARKETING AND SALES v. STATE OF JHARKHAND THROUGH THE DEPARTMENT OF ENERGY

WPC/528/2025 · 2025-04-22

Rajesh Shankar

body2025

Judgment text

Extracted from the PDF above. The PDF is authoritative.

2025:JHHC:11872-DB IN THE HIGH COURT OF JHARKHAND AT RANCHI W.P.(T) No. 528 of 2025 M/s Vijai Electricals Ltd., a Company within the meaning of section 2(20) of the Companies Act, 2013, having its Registered Office at 6-3- 648/1&2, Off Rajbhavan Road, Somajiguda, Hyderabad, through its Authorized Signatory Mr. P. Srinivasa Rao (GM-Marketing & sales), S/o Shri Ranga Rao, aged about 61 Years, resident of Paruchuri, 16- 3-21/839, Bhagath Singh Nagar, Near Raja Rajeshwari Temple, KPHВ Colony, Kukat Pally, Hyderabad, P.O. & P.S. Hyderabad, District Hyderabad, Andhra Pradesh ... ... ... Petitioner Versus 1. State of Jharkhand through the Additional Chief Secretary, Department of Energy, having its office at SBI Building, Project Bhawan, Dhurwa, Ranchi, P.O. Dhurwa, P.S. Jagannathpur, District- Ranchi, Jharkhand. 2. The Secretary-Cum-Commissioner of State Taxes, having its office at Project Bhawan, Dhurwa, Ranchi - 4, P.O. Dhurwa, P.S. Jagannathpur, District- Ranchi, Jharkhand. 3. Jharkhand Bijli Vitran Nigam Limited (JBVNL), a company incorporated under the Companies Act, having its office at Engineers Building, P.O. & P.S. Dhurwa, District-Ranchi (Jharkhand) through its Managing Director, having its place of business at Engineers Building, P.O. & P.S. Dhurwa, District- Ranchi (Jharkhand). 4. Finance Controller, JBVNL, having its office at Engineers Building, P.O. & P.S. Dhurwa, District- Ranchi (Jharkhand). 5. Chief Engineer (R.E), JBVNL, having its office at Engineers Building, P.O. & P.S. Dhurwa, District- Ranchi (Jharkhand). 6. The General Manager (Rural Project), JBVNL, has its office at Engineers Building, P.O. & P.S. Dhurwa, District- Ranchi (Jharkhand). … … ... Respondents --------- CORAM: HON’BLE THE CHIEF JUSTICE HON’BLE MR. JUSTICE RAJESH SHANKAR --------- For the Petitioner : Mr. Nitin Kumar Pasari, Advocate Ms. Sidhi Jalan, Advocate For the State: Mr. Ashok Kr. Yadav, Sr.S.C.I For the JBVNL: Mr. Sachin Kumar, Advocate Mr. Gaurav Raj, Advocate 2025:JHHC:11872-DB --------- 04/Dated: 22.04.2025 Counsel on both sides agree that the issue raised in this Writ Petition is covered by the judgment rendered by a Division Bench of this Court on 09.04.2024 in W.P.(T) No. 6712 of 2023 and batch titled “Sri Gopikrishna Infrastructure Pvt. Ltd. Vs. the State of Jharkhand and others”. Therefore, the Writ Petition is disposed of in terms of the said order. (M.S. Ramachandra Rao, C.J.) (Rajesh Shankar, J.) Sharda/MM/ Cp.02