2025 DAILYLAW 28791 (DEL)

GTL INFRASTRUCTURE LIMITED v. BHARAT SANCHAR NIGAM LIMITED

O.M.P.(MISC.)(COMM.)/718/2025 · 2025-09-02

Jyoti Singh

body2025

Judgment text

Extracted from the PDF above. The PDF is authoritative.

O.M.P.(MISC.)(COMM.) 718/2025 & connected matters $~67 to 70 * IN THE HIGH COURT OF DELHI AT NEW DELHI + O.M.P.(MISC.)(COMM.) 718/2025 GTL INFRASTRUCTURE LIMITED .....Petitioner Through: Mr. S P Mukherjee, Mr. Swarendu Das and Mr. Md. Adil Khan, Advcoates. versus BHARAT SANCHAR NIGAM LIMITED .....Respondent Through: Ms. Leena Tuteja and Ms. Ishita Kadyan, Advocates. 68 + O.M.P.(MISC.)(COMM.) 719/2025 GTL INFRASTRUCTURE LIMITED .....Petitioner Through: Mr. S P Mukherjee, Mr. Swarendu Das and Mr. Md. Adil Khan, Advcoates. versus BHARAT SANCHAR NIGAM LIMITED .....Respondent Through: Ms. Leena Tuteja and Ms. Ishita Kadyan, Advocates. 69 + O.M.P.(MISC.)(COMM.) 720/2025 GTL INFRASTRUCTURE LIMITED .....Petitioner Through: Mr. S P Mukherjee, Mr. Swarendu Das and Mr. Md. Adil Khan, Advcoates. versus BHARAT SANCHAR NIGAM LIMITED .....Respondent Through: Ms. Leena Tuteja and Ms. Ishita Kadyan, Advocates. 70 + O.M.P.(MISC.)(COMM.) 721/2025 GTL INFRASTRUCTURE LIMITED .....Petitioner This is a digitally signed order. The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 09/09/2025 at 12:15:47 O.M.P.(MISC.)(COMM.) 718/2025 & connected matters Through: Mr. S P Mukherjee, Mr. Swarendu Das and Mr. Md. Adil Khan, Advcoates. versus BHARAT SANCHAR NIGAM LIMITED .....Respondent Through: Ms. Leena Tuteja and Ms. Ishita Kadyan, Advocates. CORAM: HON'BLE MS. JUSTICE JYOTI SINGH O R D E R % 02.09.2025 1. These petitions are filed on behalf of the Petitioner under Section 29A (5) of the Arbitration and Conciliation Act, 1996 (‘1996 Act’) seeking extension of the mandate of the learned Arbitrator for a period of 12 months. 2. It is stated in the petitions that the arbitral proceedings are at the stage of recording of evidence of the Respondent. Mandate of the learned Sole Arbitrator in each of these cases has expired on 31.08.2025 as extended by this Court vide common order dated 10.09.2024. It is urged by the counsel for the Petitioner that the arbitration proceedings are a consolidation of four arbitration proceedings arising out of four different Agreements and involve complex questions and voluminous records and it is thus taking time to complete the evidence. 3. Issue notice. 4. Ms. Leena Tuteja, learned counsel for the Respondent accepts notice on behalf of the Respondent in all the petitions and on instructions, submits that Respondent has no objection to the extension of mandate of the Sole Arbitrator. 5. Accordingly, with the consent of the parties, mandate of the learned Sole Arbitrator is extended by a period of 12 months from 01.09.2025 in all This is a digitally signed order. The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 09/09/2025 at 12:15:47 O.M.P.(MISC.)(COMM.) 718/2025 & connected matters the arbitral proceedings. 6. Petitions are allowed and disposed of in the aforesaid terms. JYOTI SINGH, J SEPTEMBER 2, 2025 Ch/Shivam This is a digitally signed order. The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 09/09/2025 at 12:15:47