Research › Search › Judgment

High Court of Delhi · body

2025 DAILYLAW 26857 (DEL)

ERA INFRA ENGINEERING LIMITED v. NTPC LIMITED

O.M.P.(MISC.)(COMM.)/618/2025 · 2025-08-08

Purushaindra Kumar Kaurav

Transfer Petitionbody2025

Judgment text

Extracted from the PDF above. The PDF is authoritative.

$~O-36 * IN THE HIGH COURT OF DELHI AT NEW DELHI + O.M.P.(MISC.)(COMM.) 618/2025, I.A. 19321/2025 ERA INFRA ENGINEERING LIMITED . ....Petitioner Through: Ms. Divya Verma, Adv. versus NTPC LIMITED .....Respondent Through: Mr. Puneet Taneja, Sr. Advocate with Mr. Manmohan Singh Narula, Mr. Amit Yadav and Mr. Anil Kumar, Advs CORAM: HON'BLE MR. JUSTICE PURUSHAINDRA KUMAR KAURAV O R D E R % 08.08.2025 1. This petition has been filed for the following reliefs: “i. That (1) one year time extension be granted under Section 29A(4) read with Section 29A (5) of Arbitration & Conciliation Act, 1996 for the Arbitral Tribunal to conclude the Arbitration proceedings and pass the Arbitration Award; ii. Pass any other or appropriate order which the Hon'ble Court deem fit in the facts of the case.” 2. With the consent of the parties, the petition stands allowed in terms of prayer made herein. 3. The petition stands disposed of along with all pending applications. PURUSHAINDRA KUMAR KAURAV, J AUGUST 8, 2025/akc/sph This is a digitally signed order. The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 13/08/2025 at 12:36:07