976-ca-13435-2025.odt (1) IN THE HIGH COURT OF JUDICATURE AT BOMBAY BENCH AT AURANGABAD CIVIL APPLICATION NO. 13434 OF 2025 IN FAST/34867/2025 The Executive Engineer, Minor Irrigation Division, Jalna, Dist. Jalna VERSUS Mandakini Shivaji Ragad And Another ... Advocate for Applicant : Mr. Tekale Nikhil Shripad AGP for Respondent/State : Mr. S.P. Sonpawale Advocate for Respondent No.1 : Mr. D.A. Bhide ...
CORAM : S. G. CHAPALGAONKAR, J.
DATED : AUGUST 06, 2026 PER COURT :-
1. Heard learned advocates appearing for respective parties.
2. The applicant seeks to condone delay of 101 days caused in filing appeal.
3. Perused application and reasons stated therein. Apparently, delay is caused on account of administrative reasons which are duly explained.
4. Considering reasons as stated in application, case is made out to condone delay. Hence, application is allowed. Delay of 101 days caused in filing appeal stands condoned. First Appeal be registered subject to removal of office objections, if any.
(S.G. CHAPALGAONKAR, J.) Mujaheed// 2026:BHC-AUG:34281