GUPTA AND COMPANY DEVELOPERS PRIVATE LIMITED, THROUGH ITS MANAGING DIRECTOR JAY NARAYAN KUMAR v. UNION OF INDIA THROUGH ITS SECRETARY, MINISTRY OF ROAD TRANSPORT AND HIGHWAYS

WPC/5227/2025 · 2025-09-19

Rajesh Shankar

Writ Petition (Civil)body2025

Judgment text

Extracted from the PDF above. The PDF is authoritative.

2025:JHHC:28877-DB 1 IN THE HIGH COURT OF JHARKHAND AT RANCHI W.P.(C) No.5227 of 2025 ----- Gupta and Company Developers Private Limited, having its office at 3B2, Madhukar Regency, Shraddhanand Road, Upper Bazar, P.O. GPO, P.S. Kotwali, District Ranchi, Jharkhand through its Director Jay Narayan Kumar, son of late Nand Lal Sahu, resident of 3B2, Madhukar Regency, Shraddhanand Road, Upper Bazar, P.O. GPO, P.S. Kotwali, District Ranchi, Jharkhand. .......... Petitioner. -Versus- 1. Union of India through its Secretary, Ministry of Road Transport and Highways, Government of India, having its office at Transport Bhawan, 1 Parliament Street, New Delhi, P.O. and P.S. Parliament Street, New Delhi. 2. Regional Officer, Ministry of Road Transport and Highways, Government of India having its office at 199C, Vidyalaya Marg, Ashok Kunj, Ashok Nagar, Argora, Ranchi. 3. State of Jharkhand through its Secretary, Road Construction Department, Government of Jharkhand, having office at Project Bhawan, Dhurwa, Ranchi. 4. Chief Engineer, NH Wing, Road Construction Department, Government of Jharkhand, having office at Engineers’ Hostel, Dhurwa, Ranchi. 5. Superintending Engineer, NH Circle, Dhanbad, Road Construction Department, Government of Jharkhand, Near Kutchery, Dhanbad. 6. Executive Engineer, NH Division, Hazaribag, Road Construction Department, Government of Jharkhand having office at Behind P.T.C. Ground, Hazaribag, Jharkhand. .......... Respondents. ----- CORAM : HON’BLE THE CHIEF JUSTICE HON’BLE MR. JUSTICE RAJESH SHANKAR ----- For the Petitioner : Mr. Durgesh Agarwal, Advocate For the UOI : Mr. Abhijeet Kr. Singh, CGC For the State : Mr. Piyush Chitresh, AC to AG ----- Order No.02 Date: 19.09.2025 1. A very innocuous prayer has been made in this writ petition for grant of following relief :- “That in this writ petition, the petitioner prays for issuance of appropriate writ(s), order(s), direction(s) in the nature of mandamus directing the concerned respondents to resolve the pending issues particularly the issue of re-validation of contract as regards the work of construction of bridge in 2025:JHHC:28877-DB 2 replacement of existing narrow masonary arch culvert including its approaches over local Nala in the 67th Km of NH-100 (Job No.-100/JHR/2013-14/234) completed by the petitioner and also process and release the final bill of the petitioner dated 26.06.2024 together with the interest for delayed payment.” 2. Obviously, there can be no objection for grant of relief as prayed for by the petitioner. Accordingly, we deem it appropriate to dispose of this petition by directing that a joint meeting of the petitioner as well as the respondent nos.2 and 4 be held on 8th October, 2025 in the office of the respondent no.4 at 11:00 a.m. to resolve the issues inter se the parties. 3. The writ petition is disposed of leaving the parties to bear the costs. (Tarlok Singh Chauhan, C.J.) (Rajesh Shankar, J.) 19th September, 2025 Sanjay/Rohit