W.P.(MD)No.21766 of 2019 BEFORE THE MADURAI BENCH OF MADRAS HIGH COURT DATED : 14.11.2025
CORAM:
THE HONOURABLE MS.JUSTICE P.T.ASHA W.P.(MD)No.21766 of 2019 K.Balamurugan .. Petitioner Vs. 1.The Superintending Engineer, TANGEDCO, Sivagangai District. 2.The Executive Engineer, TANGEDCO, Manamadurai, Sivagangai District. 3.The Assistant Engineer, TANGEDCO, Thirupachathi, Thiruppuvanam Taluk, Sivagangai District.
.. Respondents
Prayer : Writ Petition filed under Article 226 of the Constitution of India, praying for issuance of Writ of Mandamus, directing the 3rd respondent to take immediate action for shifting Electricity Connection S.C.No.0320 5H.P from Survey No.117/7B to Survey No.117/7A to the petitioner's Agricultural Land and save the petitioner's Agricultural Yields situated at _________ p. 2 W.P.(MD)No.21766 of 2019 Thirupachethi Village, Thirupuvanam Taluk, Sivagangai District and in the
light
of
the
3rd respondent
proceeding
in KA.EN.OuMePo/Pa/Thi.Chethi/Ko.Ka/A.No.001/18 dated 10.04.2018. For Petitioner : Mr.D.S.Haroon Rasheed For Respondents : Mr.S.Deenadhayalan Standing Counsel
ORDER This writ petition has been filed for the following relief :
“directing the 3rd respondent to take immediate action for shifting Electricity Connection S.C.No.0320 5H.P from Survey No. 117/7B to Survey No.117/7A to the petitioner's Agricultural Land and save the petitioner's Agricultural Yields situated at Thirupachethi Village, Thirupuvanam Taluk, Sivagangai District and in the light of the 3rd respondent proceeding in KA.EN.OuMePo/Pa/Thi.Chethi/Ko.Ka/A.No.001/18
dated 10.04.2018.”
2. On instructions, the learned Standing Counsel would submit that if the documents are submitted, the petitioner's request will be considered. The petitioner also undertakes to once again produce the documents. _________ p. 3 W.P.(MD)No.21766 of 2019
3. In view of the above, the petitioner is directed to produce all the necessary documents and on receipt of the same, the respondents are
directed to consider the petitioner's representation, dated 24.04.2018 and shift the electricity service connection from Survey No.117/7B to Survey No.117/7A to the petitioner's Agricultural Land within a period of three (3) weeks therefrom.
4. With the above directions, this Writ Petition stands disposed of. No costs.
14.11.2025 NCC : Yes/No Index : Yes/No Internet : Yes gbg To 1.The Superintending Engineer, TANGEDCO, Sivagangai District. 2.The Executive Engineer, TANGEDCO, Manamadurai, Sivagangai District. _________ p. 4 W.P.(MD)No.21766 of 2019 P.T.ASHA, J. gbg 3.The Assistant Engineer, TANGEDCO, Thirupachathi, Thiruppuvanam Taluk, Sivagangai District.