Page No.# 1/6 GAHC010266182024
undefined
THE GAUHATI HIGH COURT (HIGH COURT OF ASSAM, NAGALAND, MIZORAM AND ARUNACHAL PRADESH) Case No. : WP(C)/6835/2024 BHABA KANTA NATH SON OF LATE SUNDER NATH, RESIDENT OF 243 SURAVI PATH, NEAR DPI KAHILIPARA ROAD GUWAHATI DIST KAMRUP M ASSAM VERSUS THE STATE OF ASSAM AND 2 ORS.
REPRESENTED BY ITS COMMISSIONER AND SECRETARY, GUWAHATI DEVELOPMENT DEPARTMENT, 4TH FLOOR, BLOCK D ASSAM SACHIVALAYA, DISPUR GUWAHATI 781005 2:GUWAHATI MUNICIPAL CORPORATION REPRESENTED BY ITS COMMISSIONER BHANGAGARH GMDA BUILDING GUWAHATI 781005 3:THE COMMISSIONER GUWAHATI MUNICIPAL CORPORATION BHANGAGARH GMDA BUILDING GUWAHATI 78100 Advocate for the Petitioner : ABHIJIT PATOR, J SHARMA,MR. P THAKURIA Advocate for the Respondent : SC, GDD, SC, GMC
Page No.# 2/6 BEFORE HONOURABLE MR. JUSTICE SOUMITRA SAIKIA
ORDER 14.02.2025 Heard Mr. J. Sharma, learned counsel for the petitioner. Also heard Ms. H. Baruah, learned counsel appearing on behalf of Mr. P. Nayak, learned Standing Counsel, GMC for all the respondents.
2. The petitioner’s prayer in this writ petition is for a direction to be issued to the respondent authorities to pay to the petitioner for the works done by him, pertaining to “Cleaning, Desilting of River Bahini for Ch.6300.00m to 7350.00m”.
3. The petitioner’s case in brief is that pursuant to the Invitation for Bids for Cleaning, Desilting of River Bahini for Ch.6300.00m to 7350.00m, the petitioner participated in the tender process. The respondents thereafter issued a letter of acceptance dated 18.05.2021 to the petitioner, stating that his bid at the contract price of Rs.43,37,000/- (Rupees Forty Three Lakhs Thirty Seven Thousand) had been accepted. Pursuant to the above, the respondent No. 3 issued “Issue of notice to proceed with work” dated 18.05.2021 to the petitioner vide work order no.GER/CE/1990/2021/08. The respondent No. 3 thereafter issued a show cause notice dated 08.06.2021 to the petitioner, stating that in spite of the work done by the petitioner, a majority of the drains in many areas had been inundated with rain water during the monsoon season. Further, as
Page No.# 3/6 reported by the Divisional Engineer, approximately 25-30% of the works had been found to be completed so far. As it had been observed that the petitioner would not be able to complete the work within the stipulated time, it would adversely affect public health and endanger public life and property, he was asked to show cause as to why the contract agreement should not be terminated.
4. The petitioner thereafter submitted a reply dated 10.06.2021 to the show cause-notice, stating that 50% of the first phase of the contract work had been completed and he would definitely be able to complete the work within the stipulated time. The respondent No. 3 however terminated the contract agreement with the petitioner, vide letter dated 12.06.2021.
5. The petitioner’s counsel submits that similarly situated persons, whose contract works were similar to the petitioner and whose contract agreements had also been terminated, had approached this Court by filing WP(C) Nos. 3164/2021 and 3397/2021. A Co-ordinate Bench of this Court, vide a common
order dated 20.12.2022, disposed of the same by directing the respondents to undertake a verification exercise, which would include the measurement of the works done. Thereafter, payment was to be made, in terms of the measurement undertaken. He further submits that the direction passed in WP(C) Nos. 3164/2021 and 3397/2021 should also be issued in this case.
Page No.# 4/6
6. Ms. H. Baruah, learned counsel for the respondents, on the other hand, submits that as three monsoon seasons have already passed since termination of the petitioner’s contract work, it would be impossible to measure the works done by the petitioner. She accordingly submits that the direction passed, vide
order dated 20.12.2022 in WP(C) Nos. 3164/2021 and 3397/2021, cannot be made applicable to the facts of this case. 7. I have heard the learned counsels for the parties. 8. As can be seen from the pleadings and the submissions made by the parties, the petitioner had been given the contract for clearing, desilting of River Bahini. The petitioner’s contract agreement had been terminated by the respondent No. 3 on 12.06.2021. The petitioner has not made a challenge to the same, except by way of this writ petition, which had been filed only on 17.12.2024. As three monsoon seasons having already passed since the termination of the petitioner’s contract agreement, it is quite apparent that the work done by the petitioner, prior to 12.06.2021 on the river cannot be measured as on date. As such, the directions passed by a Co-ordinate Bench vide the order dated 20.12.2022 in WP(C) Nos. 3164/2021 and 3397/2021 cannot be made applicable to this case. Further, in the order dated 20.12.2022, the Co-ordinate Bench has held that the said order would not be a precedent for other works. There is another aspect of the matter, for which this Court is of the view that the directions passed for
Page No.# 5/6 measuring the works of the petitioners in WP(C) Nos. 3164/2021 and 3397/2021, cannot be applied to the facts of this case, i.e., in view of the petitioner being a fence sitter. 9. In the case of State of Uttar Pradesh and others vs. Arvind Kumar Srivastava and others, reported in (2015) 1 SCC 347, the Supreme Court has held that when a particular set of employees is given relief by the Court, all other identically situated persons need to be treated alike by extending that benefit, which has been given to the particular set of employees. Otherwise, it would be violative of Article 14 of the Constitution. The Supreme Court further held that this principle is however subject to well recognized exceptions in the form of laches and delays as well as acquiescence. They would be treated as fence- sitters and laches, delays and acquiescence would be a valid ground to dismiss their claim. In the present case, the petitioner herein is a fence sitter and is trying to take the benefit of the order passed in WP(C) Nos. 3164/2021 and 3397/2021. 10.
The above being said, the letter dated 12.06.2021 issued by the respondent No. 3, terminating the petitioner’s contract agreement, states that the executed quantity of work undertaken by the petitioner till 12.06.2021 would be measured within a short notice by the concerned Divisional Engineer in presence of 3rd party monitoring agency engaged by the GMC. Page No.# 6/6
11. In view of the said statement made in the letter dated 12.06.2021, this Court is of the view that the petitioner should be paid for the amount of work executed by him, as measured by the respondents, in terms of the letter dated 12.06.2021 issued by the respondent No. 3. 12. At this stage, the petitioner’s counsel submits that the petitioner would be satisfied if a direction is issued to the respondent authorities, to pay to the petitioner for the amount of work done by him, as measured by the concerned Divisional Engineer, in presence of a 3rd party monitoring agency engaged by the GMC, in terms of the letter dated 12.06.2021. 13. Accordingly, in view of the above, this Court directs the respondents, more particularly, the respondent No. 3, to pay to the petitioner the executed quantity of work done, as measured by the concerned Divisional Engineer, in presence of 3rd party monitoring agency engaged by the GMC, in terms of the letter dated
12.06.2021. The entire exercise should be concluded and payment made to the petitioner for the amount of work done by him, within a period of 6 (six) months from the date of receipt of a certified copy of this order. 14. With the above directions, this writ petition is accordingly disposed of. JUDGE Comparing Assistant