M/s.Sri.Venkateswar Constructions v. THE STATE OF ANDHRA PRADESH
WP/24743/2025 · 2026-07-06
Ravi Cheemalapati
body2025
DailyLaw.ai
[ 2025 DAILYLAW 2129 (AP) · dailylaw.ai ]
DailyLaw.ai
[ 2025 DAILYLAW 2129 (AP) · dailylaw.ai ]
Judgment text
Extracted from the PDF above. The PDF is authoritative.
APHC010469112025
IN THE HIGH COURT OF ANDHRA PRADESH TUESDAY, THE 7 THE HONOURABLE SRI JUSTICE RAVI CHEEMALAPATI WRIT PETITION NO: 24743/2025 Between:
1. M/S.SRI.VENKATESWAR CONSTRUCTIONS, REP.BY MANAGING PARTNER KAMOORI MANOHAR S/O. K. RAMANA REDDY, AGE 32 YEARS, R/O.1-58, KRISHNAMPALLI, SPSR NELLORE DISTRICT. 1. THE STATE OF ANDHRA PRADESH, REP BY ITS PRINCIPAL SECRETARY, ROADS SECRETARIAT BUILDING, VELAGAPUDI, AMARAVATHI, GUNTUR. 2. THECHIEF ENGINEERR AND B, RSW AND
BUILDINGS, VIJAYAWADA. 3. THE EXECUTIVE ENGINEERRAND B, (ROADS AND BUILDINGS) DIVISION , KAVALI,NELLORE DISTRICT. 4. THE STATE OF ANDHRA PRADESH, REP. BY ITS PRINCIPAL SECRETARY DEPARTMENT OF FINANCE AND PLANNING, SECRETARIAT BUILDINGS, VELAGAPUDI, AMARAVATHI, GUNTUR DISTRICT. Petition under Article 226 of the Constitution of India praying that in the circumstances stated in the affidavit filed therewith, the High Court may be pleased to issue an appropriate Writ Order or direction more particularly one in the nature of Writ of Mandamus declaring the action of the Respondents in withholding the payments of pending amounts of Rs. 26,44,072/ Lakhs, Forty our thousand, Seventy Two Rupees only) even after finalizing IN THE HIGH COURT OF ANDHRA PRADESH AT AMARAVATI (Special Original Jurisdiction) TUESDAY, THE 7th DAY OF JULY 2026 PRESENT THE HONOURABLE SRI JUSTICE RAVI CHEEMALAPATI WRIT PETITION NO: 24743/2025 M/S.SRI.VENKATESWAR CONSTRUCTIONS, REP.BY MANAGING PARTNER KAMOORI MANOHAR S/O. K. RAMANA REDDY, AGE 32 58, KRISHNAMPALLI, SPSR NELLORE DISTRICT. ...PETITIONER AND THE STATE OF ANDHRA PRADESH, REP BY ITS PRINCIPAL SECRETARY, ROADS AND BUILDINGS(RAND B) DEPARTMENT, SECRETARIAT BUILDING, VELAGAPUDI, AMARAVATHI, GUNTUR. THECHIEF ENGINEERR AND B, RSW AND
BUILDINGS, THE EXECUTIVE ENGINEERRAND B, (ROADS AND BUILDINGS) DIVISION , KAVALI,NELLORE DISTRICT. HE STATE OF ANDHRA PRADESH, REP. BY ITS PRINCIPAL SECRETARY DEPARTMENT OF FINANCE AND PLANNING, SECRETARIAT BUILDINGS, VELAGAPUDI, AMARAVATHI, GUNTUR ...RESPONDENT(S): Petition under Article 226 of the Constitution of India praying that in the circumstances stated in the affidavit filed therewith, the High Court may be pleased to issue an appropriate Writ Order or direction more particularly one f Mandamus declaring the action of the Respondents in withholding the payments of pending amounts of Rs. 26,44,072/ Lakhs, Forty our thousand, Seventy Two Rupees only) even after finalizing IN THE HIGH COURT OF ANDHRA PRADESH [3332] THE HONOURABLE SRI JUSTICE RAVI CHEEMALAPATI M/S.SRI.VENKATESWAR CONSTRUCTIONS, REP.BY MANAGING PARTNER KAMOORI MANOHAR S/O. K. RAMANA REDDY, AGE 32 58, KRISHNAMPALLI, SPSR NELLORE DISTRICT. ...PETITIONER THE STATE OF ANDHRA PRADESH, REP BY ITS PRINCIPAL AND BUILDINGS(RAND B) DEPARTMENT, SECRETARIAT BUILDING, VELAGAPUDI, AMARAVATHI, GUNTUR.
THECHIEF ENGINEERR AND B, RSW AND
BUILDINGS, THE EXECUTIVE ENGINEERRAND B, (ROADS AND BUILDINGS) HE STATE OF ANDHRA PRADESH, REP. BY ITS PRINCIPAL SECRETARY DEPARTMENT OF FINANCE AND PLANNING, SECRETARIAT BUILDINGS, VELAGAPUDI, AMARAVATHI, GUNTUR ...RESPONDENT(S): Petition under Article 226 of the Constitution of India praying that in the circumstances stated in the affidavit filed therewith, the High Court may be pleased to issue an appropriate Writ Order or direction more particularly one f Mandamus declaring the action of the Respondents in withholding the payments of pending amounts of Rs. 26,44,072/- (Twenty Six Lakhs, Forty our thousand, Seventy Two Rupees only) even after finalizing
2
the bills payable to the petitioner in relation to the works i.e. I. Renovation of Existing Inspection Bungalow at Kndukur (New) in SPSR Nellore District Agreement no.81/2023-24,Dt 29-02-2024 and pass any other order or orders as this Honble Court may deem fit and proper in the interest of Justice. IA NO: 1 OF 2025 Petition under Section 151 CPC praying that in the circumstances stated in the affidavit filed in support of the petition, the High Court may be pleased to direct the respondents to forthwith consider releasing the amounts Rs. 26,44,072/- (Twenty Six Lakhs, Forty Four thousand. Seventy Two Rupees only) payable to the petitioner herein, pending disposal of the writ petition and pass such Counsel for the Petitioner:
1. DEVASRI ROSHAN KANCHARLA Counsel for the Respondent(S):
1. GP FOR ROADS BUILDINGS
2. GP FOR FINANCE PLANNING
3
The Court made the following order: The grievance of the petitioner is that even after finalization of the bills payable to the petitioner in relation to the works i.e., ‘Renovation of Existing Inspection Bungalow at Kandukur (New) in SPSR Nellore district vide Agreement No.81/2023-24, dated 29.02.2024, the respondent authorities are withholding the payments of pending amount of Rs.26,44,072/-
2. Heard Sri Devasri Roshan Kancharla, learned counsel for the petitioner, learned Assistant Government Pleader for Roads and Buildings Department and learned Assistant Government Pleader for Finance Department. 3.
Learned counsel for the petitioner, in elaboration to what has been stated in the affidavit, contended that despite the completion of the contractual work and the finalization of the bills payable to the petitioner, the respondent authorities have failed to release the amounts. Hence, prayed to pass appropriate orders protecting the interest of the petitioner.
4. Learned Assistant Government Pleader for Roads and Buildings Department, while reiterating the contents of the counter affidavit of respondent No.3, contended that the authorities have admitted the bills of the petitioner and that the bill has been uploaded in NIDHI portal vide CFMS Bill No.2025-2282836 and the status of the bill was shown as ‘Waiting for fund clearance’, however sought three months’ time for release of the admitted amount payable to the petitioner.
4
5. To the said submission, learned counsel for the petitioner reported no objection and prayed to pass appropriate orders in that regard.
6. In view of the facts and circumstances of the case and taking the
submissions of learned counsel for the parties into consideration, as the authorities have expressed their intention to pay the entitled amount to the petitioner, there is no purpose in keeping this Writ Petition pending. As such, this Court is inclined to dispose of the same, with the consent of both the parties, at the admission stage itself, by passing the following order:
“The respondent authorities are directed to pay an amount of Rs.26,44,072/- (Rupees Twenty Six Lakhs Forty Four Thousand, Seventy Two only) to the petitioner within a period of three (3) months from the date of receipt of a copy of this order.”
7. Accordingly, the Writ petition is disposed of. There shall be no order as to costs.
As a sequel thereto, interlocutory applications pending, if any in the Writ Petition, shall also stand closed. ____________________________ JUSTICE RAVI CHEEMALAPATI
07.07.2026 MP
5
123
THE HON’BLE SRI JUSTICE RAVI CHEEMALAPATI
WRIT PETITION NO.24743 OF 2025 07.07.2026
MP