IN THE HIGH COURT OF ANDHRA PRADESH AT AMARAVATI (Special Original Jurisdiction) [3330] THURSDAY, THE FOURTH DAY OF SEPTEMBER TWO THOUSAND AND TWENTY FIVE
PRESENT THE HONOURABLE SRI JUSTICE TARLADA RAJASEKHAR RAO
CONTEMPT CASE NO: 1491/2025 Between:
1. GONUGUNTA RAMBABU, S/O.G.PENCHALAIAH, AGE 55 YEARS, VAVILERU, CHEJERLA, SPSR NELLORE, ANDHRA PRADESH.
...PETITIONER AND
1. SRI SHASHIBHUSHAN KUMAR, PRINCIPAL SECRETARY, TO PANCHAYATRAJ AND RURAL DEVELOPMENT DEPARTMENT, SECRETARIAT, VELAGAPUDI, AMARAVATHI, GUNTUR. - 522 503.
2. SRI T VENUGOPAL, PROJECT DIRECTOR, HOUSING CORPORATION, SPSR NELLORE DISTRICT.
3. SRI PEEYUSH KUMAR, PRINCIPAL SECRETARY, FINANCE AND PLANNING DEPARTMENT,
SECRETARIAT, VELAGAPUDI, AMARAVATHI, GUNTUR. - 522 503
4. SRI L SREEDHARREDDY, DISTRICT PANCHAYAT OFFICER, SPSR NELIORE DISTRICT.
5. SRI B GANGABHAVANI, PROJECT DIRECTOR, MGNREGS SCHEME, SPSR NELIORE DISTRICT.
6. SRL N VIJAYALALITHA MPDO, CHEJERLA MANDAL, SPSR NELIORE DISTRICT.
7. SRI B RAMAIAH, KAVILERU GRAMA PANCHAYAT, PANCHAYAT SECRETARY, CHEJERLA MANDAL, NELIORE DISTRICT.
8. SRI P RAJA BABU, COMMISSIONER AND DIRECTOR OF A.P.STATE HOUSING CORPORATION, VIJAYAWADA.
...CONTEMNOR(S)
Petition under Sections 10 to 12 of Contempt of Courts Act 1971 praying that in the circumstances stated in the affidavit file herein the High Court may be pleased to punish the respondent herein for the willful, deliberate and wanton violation of the orders dt. 24.01.2025 of this Hon’ble Court made in WP. No. 27486/2024 and pass
2 Counsel for the Petitioner:
1. DEVASRI ROSHAN KANCHARLA
Counsel for the Contemnor(S):
1. KALYAN CHAKRAVARTHY R
2. RAMA RAO KOCHIRI
3. Mattegunta.Sudhir,Standing Counsel For Z.P.Ps,M.P.Ps,Gram Panchayats
The Court made the following:
3 THE HONOURABLE SRI JUSTICE TARLADA RAJASEKHAR RAO
CONTEMPT CASE NO.1491 of 2025 ORDER:
The learned counsel appearing for the respondents would submit that the order dated 24.01.2025 passed in W.P.No.27486 of 2024 by this Court has been complied with and also filed receipt to that extent that on 28.08.2025 payment was made for the work executed by the petitioner.
As order of this Court has been complied with by the respondents, the Contempt Case is closed. There shall be no order as to costs.
As a sequel, interlocutory applications, if any pending in this contempt case shall stand closed.
___________________________________ JUSTICE TARLADA RAJASEKHAR RAO Date: 04.09.2025 SPP
4
THE HON’BLE SRI JUSTICE TARLADA RAJASEKHARA RAO
C.C.No.1491 OF 2025
Date: 04.09.2025
SPP