HIGH COURT OF JUDICATURE AT ALLAHABAD LUCKNOW APPLICATION U/S 529 BNSS No. - 61 of 2025 Court No. - 16 HON'BLE BRIJ RAJ SINGH, J.
1. Heard learned counsel for the applicant and learned AGA for the State.
2. The applicant has approached this Court for getting a direction issued to the court of Additional Court no.2, Lucknow, to decide the Complaint Case no.7722 of 2025 (Pramod Telecom Private Limited vs. Syska LED Lights Private Limited and others) filed under Section 138 of Negotiable Instrument Act.
3. The aforesaid case of the applicant is pending since the year
2024. Learned counsel for the applicant submits that under Section 143(3) of the N.I. Act, it is provided that every trial under this Section shall be conducted as expeditiously as possible and an endeavour shall be made to conclude the trial within six months from the date of filing of the complaint. He has submitted that since long time, the case is pending without substantial progress.
4. In view of the aforesaid facts, the court concerned is directed Versus Counsel for Applicant(s) : Rishabh Raj, Vedant Bhargava Counsel for Opposite Party(s) : G.A. Pramod Telecom Pvt. Ltd. Thru. Its Director, Mr. Dhruva Chandra .....Applicant(s) State Of U.P. Thru. Prin. Secy. Deptt. Of Home Lko. And 3 Others .....Opposite Party(s)
to adhere to the provisions of Section 143(3) of the N.I. Act and accordingly expedite the proceedings of the aforesaid case in accordance with law.
5. This application stands disposed of. October 15, 2025 Sachin NA529 No. 61 of 2025 2 (Brij Raj Singh,J.) Digitally signed by :- SACHIN MEHROTRA High Court of Judicature at Allahabad, Lucknow Bench