DUKHI DAS AND ANOTHER v. UNION OF INDIA AND ANOTHER
WRIC/36374/2025 · 2025-10-16
body2025
DailyLaw.ai
[ 2025 DAILYLAW 192890 (ALL) · dailylaw.ai ]
DailyLaw.ai
[ 2025 DAILYLAW 192890 (ALL) · dailylaw.ai ]
Judgment text
Extracted from the PDF above. The PDF is authoritative.
HIGH COURT OF JUDICATURE AT ALLAHABAD WRIT - C No. - 36374 of 2025 Court No. - 5 HON'BLE MANISH KUMAR NIGAM, J.
1. Heard Sri Shiv Babu Dubey, learned counsel for the petitioners, Ms. Swarn Lata Suman, learned counsel for the respondent no. 1 and perused the record.
2. The solitary grievance of the petitioners is that only Rs. 80,000/- of the amount has been
directed to be released in favour of the claimants/petitioners by the impugned award of the Railway Accident Claims Tribunal dated 08.08.2025 is inequitable, unjust and grossly inadequate. It defeats the purpose of award of compensation for death caused to the son of the petitioners in a railway accident.
3. A perusal of the record reveals that in a railway accident occurred on 03.05.2015, Munna Kumar son of petitioners suffered fatal injuries and died on spot. Arising therefrom, the petitioners instituted a claim petition on 22.12.2015 which has been decided on 08.08.2025, almost ten years after the occurrence of the accident. Even then, by that award, the Tribunal has awarded Rs. 8,00,000/- (Rs. 4,00,000/- has been awarded to petitioner no. 1(father) Rs. 4,00,000/- has been awarded to petitioner no. 2 (mother).
4. The Tribunal has provided for release of Rs. 80,000/- to the petitioners and the balance is to be deposited in Fixed Deposit for a period of three years.
5. Petitioners are aggrieved by the wholly inadequate amount directed to be released, in a mechanical manner. Looking at the total compensation awarded, a sum of Rs. 80,000/-would be released at present though the Versus Counsel for Petitioner(s) : Shiv Babu Dubey Counsel for Respondent(s) : A.S.G.I. Dukhi Das And Another .....Petitioner(s) Union Of India And Another .....Respondent(s)
petitioners claim that compensation of Rs. 8,00,000/- has been awarded. At present, the petitioners pray for release of hundred per cent of the awarded amount to the petitioners.
6. On the other hand, learned counsel for the Railways would submit that the
order restraining release of ninety per cent of the award is only in the interest of the petitioners as they are likely to receive a higher amount after three years upon accrual of interest. 7. Having heard learned counsel for the parties and having perused the record, while there can be no dispute to the principle universally applied in such cases where part compensation amount is released at the time of the award being made and the balance amount is invested for the benefit of the claimants, at the same time, it cannot be applied as a rule of thumb in all cases. In that, individual facts and circumstances must dictate the exercise of discretion, in such matters. The claimants/petitioners who lost their son and on whom certain dependency may also be claimed cannot be forced to litigate for years to earn an award of compensation and then be made to wait for further years to receive that compensation owing to exercise of discretion by the Court, ostensibly in the interest of such claimants. 8. Therefore, the above principle invoked by the learned Tribunal must be blended with practicality so as to release a reasonable amount, keeping in mind the overall circumstances of the case. 9. In the present case, petitioner No. 1 is the father of the deceased is aged about 72 years and petitioner No. 2 is mother of the deceased respectively. They have waited for ten years from the occurrence of death for award of the compensation. The compensation awarded at the moment is also not excessive but a modest sum of Rs. 8,00,000/-. 10. Accordingly, the prayer made by learned counsel for the petitioners for release of hundred per cent of the awarded amount to the petitioners, is found to be wholly just and proper. Accordingly, the award dated 08.08.2025, shall stand modified. 11. Let 100% of the awarded amount i.e. Rs. 8,00,000/- along with proportionate interest be released in favour of the petitioners (Rs. 4,00,000/- WRIC No. 36374 of 2025 2
each to both the petitioners) within a period of four weeks from the date of production of certified copy of this order. 12. With the above observations, the present writ petition is disposed of. 13. It is made clear that any amount paid in compliance of the award may be adjusted against the amount to be released in pursuance of this order. 14.
Also, this order has been passed independent of the right of the petitioners to claim enhancement, if advised. October 17, 2025 Ved Prakash WRIC No. 36374 of 2025 3 (Manish Kumar Nigam,J.) Digitally signed by :- VED PRAKASH SHARMA High Court of Judicature at Allahabad Digitally signed by :- VED PRAKASH SHARMA High Court of Judicature at Allahabad