THE EX. ENGINEER, OSMANABAD MEDIUM PROJECT DIV. OSMANABAD AND ORS v. SUBRAO BABADEO PAWAR
CA/8292/2022 · 2025-04-03
Shri Neeraj P Dhote
body2025
DailyLaw.ai
[ 2025 DAILYLAW 19021 (BOM) · dailylaw.ai ]
DailyLaw.ai
[ 2025 DAILYLAW 19021 (BOM) · dailylaw.ai ]
Judgment text
Extracted from the PDF above. The PDF is authoritative.
911-CA-8292-22.odt IN THE HIGH COURT OF JUDICATURE OF BOMBAY BENCH AT AURANGABAD 911 CIVIL APPLICATION NO. 8292 OF 2022 IN FAST/16994/2021 THE EX. ENGINEER, OSMANABAD MEDIUM PROJECT DIV.
OSMANABAD AND ORS VERSUS SUBRAO BABADEO PAWAR …. Mr. Ruturaj C. Patil and Mr. R. A. Tambe, Advocates for the Applicants Mr. Akash E. Madne h/for Mr. A. B. Kale, Advocate for the Respondent ….
CORAM : NEERAJ P. DHOTE, J.
DATE : 03.04.2025 PER COURT :-
1. This is an Application for condonation of 913 days delay in preferring the Appeal against the Judgment and Award dated 16.06.2017 passed by the learned Civil Judge Senior Division, Bhoom, Dist. Osmanabad in L.A.R. No.296 of 2014.
2. The Applicant is the Acquiring Body. It is submitted by the learned Advocate for the Applicant that sufficient reasons are shown in the Application due to which the Appeal could not be filed within the prescribed period. He submits that the delay be condoned and the Appeal can be heard on merits. 1 of 2 2025:BHC-AUG:10102
(( 2 )) 911-CA-8292-22
3. The learned Advocate for the Respondent submits that appropriate order be passed.
4. After hearing both sides and going through the Application, for the reasons stated in the Application in Paragraph Nos.2 and 3 the Application is allowed in terms of prayer clause ‘a’ subject to deposit of costs of Rs.500/- by the Applicants with the Bar Association of the learned Reference Court.
[ NEERAJ P. DHOTE, J.] HRJadhav 2 of 2