APHC010262472023
IN THE HIGH COURT OF ANDHRA PRADESH AT AMARAVATI (Special Original Jurisdiction) [3459] FRIDAY, THE TWENTY FOURTH DAY OF JANUARY TWO THOUSAND AND TWENTY FIVE PRESENT THE HONOURABLE SMT JUSTICE SUMATHI JAGADAM CONTEMPT CASE TRANSFERED FROM APAT NO: 290/2023 Between: N Eswara Reddy ...PETITIONER AND Sri M Venkateswara Rao and Others ...RESPONDENT(S) Counsel for the Petitioner:
1. M R TAGORE Counsel for the Respondent(S):
1. RAMALINGESWARA RAO KOCHARLA KOTA The Court made the following:
ORDER: The above Contempt Case is filed complaining the non-implementation of the order, dated 03.07.2017, passed by the Andhra Pradesh Administrative Tribunal in O.A.No.4232 of 2015.
2. Learned Government Pleader for Services-II submits that the Superintending Engineer & DWRO, Telugu Ganga Project Circle, Nandyal i.e., the 2nd respondent, addressed a letter to the Government Pleader vide Letter No. SE/TGP/NDL/AB/Supdt/A.3/443M, dated 25.07.2024, informing that the petitioner was paid an amount of Rs.1,80,248/- for the interregnum period from 01.02.2014 to 04.02.2015 vide payment reference No.2421822412848, dated 29.08.2018, by enclosing the statement of supplementary pay bill. The instructions of the 2nd respondent are handed over to the learned counsel for the petitioner in the Court.
3. Learned counsel for the petitioner submits that he could not get instructions from the petitioner and requested to close the Contempt Case with liberty to challenge the letter dated 25.07.2024, if the amount is not credited to the petitioner’s account.
4. Recording the said submissions, the Contempt Case (AT) is closed, granting liberty as prayed for. No order as to costs. As a sequel, miscellaneous petitions, if any, pending shall stand closed.
___________________________
JUSTICE SUMATHI JAGADAM Date: 24.01.2025 KAS
144
THE HONOURABLE SMT JUSTICE SUMATHI JAGADAM
CONTEMPT CASE TRANSFERRED FROM APAT NO: 290/2023
Date: 24.01.2025 KAS