W.P.No.3011 of 2025 IN THE HIGH COURT OF JUDICATURE AT MADRAS Dated 29.01.2025
CORAM:
THE HONOURABLE MR.JUSTICE S.SOUNTHAR W.P.No.3011 of 2025 S.Praveen ... Petitioner Vs.
1. The District Collector, Namakkal District, Namakkal.
2. The Chairman cum Managing Director, Tamilnadu General and Distribution Corporation Ltd., Anna Salai, Chennai 600 002.
3. The Chief Engineer, Civil/Transmission, Anna Salai, Chennai 600 002.
4. The Superintending Engineer, General Construction Circle, Salem 636 014.
5. The Executive Engineer, Transmission Line Construction, TANTRANSCO (TNEB), Udayapatty, Salem 636 014.
... Respondents Prayer: Writ petition filed under Article 226 of Constitution of India seeking for issuance of Writ of Mandamus directing the first respondent to consider and dispose of the petitioner's representation https://www.mhc.tn.gov.in/judis
W.P.No.3011 of 2025 dated 03.01.2025, seeking for erection of tower No.35(serial No.37) on Unjanai-Nallur Transmission project in between the Tower No.34 and 36 (Serial No.36 and 38) connecting on a straight line approved by the Electrical approval Committee. For Petitioner : Mr.S.Angamuthu For Respondents : Mr.D.R.Arunkumar, Standing Counsel for respondents 2 to 5.
ORDER The petitioner herein seeks a direction to the first respondent to consider and dispose of the petitioner's representation dated 03.01.2025, seeking erection of tower No.35(serial No.37) on Unjanai- Nallur Transmission project in between the Tower No.34 and 36 (Serial No.36 and 38) in a straight line approved by the Electrical approval Committee.
2. The petitioner is the owner of the property situate in S.No.403/2B and 403/3B in Maniyanur Village, Paramathivelur Taluk, Namakkal District. He has got certain grievance with regard to the deviation of plan in erecting electricity transmission towers for transmitting power from the existing Unjanai Sub Station to the https://www.mhc.tn.gov.in/judis
W.P.No.3011 of 2025 Nallur Sub station. Hence, he submitted a representation to the respondents on 03.01.2025, requesting them to erect the Tower No.35 (Sl.No.37), as per the approved plan by the Electricity Board. The said representation has not been considered. Therefore, the petitioner has come before this court.
3. Mr.D.R.Arunkumar, learned Standing Counsel, who takes notice for respondents 2 to 5 would submit that the representation submitted by the petitioner dated 03.01.2025 will be considered and orders will be passed in accordance with law by the fourth respondent, within a time stipulated by this court.
4. In view of the submission made by the learned Standing Counsel, without going into the merits of the claim made by the petitioner, this court is inclined to direct the fourth respondent to consider the representation of the petitioner dated 03.01.2025 and pass final orders on its own merits and in accordance with law, within a period of four weeks from the date of receipt of copy of the order. https://www.mhc.tn.gov.in/judis
W.P.No.3011 of 2025
5. With the above direction, this writ petition is disposed of. There shall be no order as to costs. 29.01.2025 Index:Yes/No Internet:Yes/No mst To
1. The District Collector, Namakkal District, Namakkal.
2. The Chairman cum Managing Director, Tamilnadu General and Distribution Corporation Ltd., Anna Salai, Chennai 600 002.
3. The Chief Engineer, Civil/Transmission, Anna Salai, Chennai 600 002.
4. The Superintending Engineer, General Construction Circle, Salem 636 014.
5. The Executive Engineer, Transmission Line Construction, TANTRANSCO (TNEB), Udayapatty, Salem 636 014. https://www.mhc.tn.gov.in/judis
W.P.No.3011 of 2025 S.SOUNTHAR, J. mst W.P.No.3011 of 2025 29.01.2025
https://www.mhc.tn.gov.in/judis