Judgment text
Extracted from the PDF above. The PDF is authoritative.
IN THE HIGH COURT OF PUNJAB AND HARYANA AT CHANDIGARH 108
EDELWEISS ASSET RECONSTRUCTION COMPANY LIMITED THROUGH ITS AUTHORIZED OFFICER
ADDITIONAL DISTRICT MAGISTRATE MOGA AND OTHERS
CORAM: HON’BLE MR. JUSTICE ANUPINDER SINGH GREWAL
HON’BLE MS. JUSTICE VIKRAM AGGARWAL
Present: Ms. Sulochna Bohra
ANUPINDER SINGH GREWAL, J. (ORAL)
The p execute the order dated under Section 14 of the secured asset to the petitioner.
2.
Issue notice to respondents
3.
At the asking of the Court, Mr. Punjab, accepts notice on behalf of respondents
4.
Heard
5.
In view of the limited prayer
disposed of with by respondent No.1 on preferably within a period of copy of this order.
24.01.2025 SwarnjitS
Whether speaking/reasoned
Whether reportable
IN THE HIGH COURT OF PUNJAB AND HARYANA AT CHANDIGARH
CWP-1976-2025
DATE OF DECISION: 24.01.2025
EDELWEISS ASSET RECONSTRUCTION COMPANY LIMITED THROUGH ITS AUTHORIZED OFFICER
Versus ADDITIONAL DISTRICT MAGISTRATE MOGA AND OTHERS
HON’BLE MR. JUSTICE ANUPINDER SINGH GREWAL HON’BLE MS. JUSTICE VIKRAM AGGARWAL Ms. Sulochna Bohra, Advocate for the petitioner.
ANUPINDER SINGH GREWAL, J. (ORAL) The petitioner is seeking direction execute the order dated 08.05.2024 (Annexure P under Section 14 of the SARFAESI Act for handing over the physical possession of the secured asset to the petitioner.
Issue notice to respondents No.1 to 3 only at this sta At the asking of the Court, Mr. Aftab Singh Khara, Senior DAG, , accepts notice on behalf of respondents No.1 to 3 Heard. In view of the limited prayer of the petitioner
disposed of with a direction to respondent No.2 to ensure that the order passed by respondent No.1 on 08.05.2024 (Annexure P within a period of two months from the date of receipt of certified copy of this order.
(ANUPINDER SINGH GREWAL)
(VIKRAM AGGARWAL)
Whether speaking/reasoned : Yes / No Whether reportable
: Yes / No IN THE HIGH COURT OF PUNJAB AND HARYANA AT CHANDIGARH 2025
DATE OF DECISION: 24.01.2025 EDELWEISS ASSET RECONSTRUCTION COMPANY LIMITED
… Petitioner (s) ADDITIONAL DISTRICT MAGISTRATE MOGA AND OTHERS
... Respondent(s) HON’BLE MR. JUSTICE ANUPINDER SINGH GREWAL HON’BLE MS. JUSTICE VIKRAM AGGARWAL , Advocate for the petitioner.
etitioner is seeking directions to respondents No.1 to 3 to (Annexure P-2) passed by respondent No.1 for handing over the physical possession No.1 to 3 only at this stage. Aftab Singh Khara, Senior DAG, No.1 to 3. of the petitioner, this petition is 2 to ensure that the order passed (Annexure P-2) is executed expeditiously, two months from the date of receipt of certified (ANUPINDER SINGH GREWAL)
JUDGE (VIKRAM AGGARWAL)
JUDGE Yes / No Yes / No
EDELWEISS ASSET RECONSTRUCTION COMPANY LIMITED
... Respondent(s) to ) passed by respondent No.1 for handing over the physical possession Aftab Singh Khara, Senior DAG, , this petition is 2 to ensure that the order passed is executed expeditiously, two months from the date of receipt of certified SWARNJIT SINGH 2025.01.24 14:42 I attest to the accuracy and integrity of this document