W.P(MD)No.26654 of 2025 BEFORE THE MADURAI BENCH OF MADRAS HIGH COURT DATED: 25.09.2025 CORAM THE HONOURABLE MS.JUSTICE P.T.ASHA Writ Petition(MD)No.26654 of 2025 and W.M.P(MD)No.20655 of 2025 PSY Resource India Ltd. S.F.No.264/1, Virathanur, Madurai – 625 022. rep. by its Director V.Ramdoss
..Petitioner
Vs
1. Tamil Nadu Power Distribution Corporation Limited (TNPDCL) 10th Floor, 144, Anna Salai, Chennai - 600 002, Represented by its Chairman and Managing Director. 2. The Superintending Engineer Madurai / Metro Electricity Distribution Circle, Tamil Nadu Generation and Distribution Corporation Limited, Madurai. 3. Sunrays Textiles Process Private Limited No.15, Bose Street, Sellur, Madurai - 625 002. ..Respondents 1/5 https://www.mhc.tn.gov.in/judis
W.P(MD)No.26654 of 2025 Prayer: Writ Petition filed under Article 226 of the Constitution of India, praying this Court to issue a Writ of Mandamus, directing the 2nd respondent to effect a new temporary LT service connection as per petitioner's application dated 20.08.2025 without referring to WP (MD) No. 13173 of 2024 filed by the 3rd respondent herein, as per the 1st respondents circular memo dated 23.01.2014. For Petitioner : Mr.V.Nirmalkumar For Respondents : Mr.S.Deenadhayalan Standing Counsel (for R1 and R2)
ORDER The petitioner seeks a direction to the second respondent to effect a new temporary LT service connection as per the petitioner’s application dated 20.08.2025, without reference to W.P. (MD) No.13173 of 2024 filed by the third respondent herein, in accordance with the first respondent’s circular memo dated 23.01.2014. 2. Mr.S.Deenadhayalan, learned standing counsel takes notice for the respondents 1 and 3. Since no adverse order is going to be passed as against the third respondent, notice to them is dispensed with. By consent, this writ petition is taken up for final disposal at the stage of admission itself. 2/5 https://www.mhc.tn.gov.in/judis
W.P(MD)No.26654 of 2025
3. According to the petitioner, they are a private company, and they made an application dated 20.08.2025 seeking a new temporary LT service connection. Since the said application has not been considered, the petitioner has approached this Court. 4. The learned Standing Counsel appearing for respondents 1 and 2 would submit that the petitioner’s application will be considered in accordance with law, subject to the outcome of the writ petition in W.P. (MD) No.13173 of 2024. 5.
In view of the above, without expressing any opinion on the merits of the matter, the application of the petitioner dated 20.08.2025 shall be considered, and a final order shall be passed on its own merits after affording a reasonable opportunity to the petitioner and the third respondent, and subject to the result of W.P. (MD) No.13173 of 2024. 6. Accordingly, this Writ Petition is allowed. No costs. Consequently, connected miscellaneous petition is closed. 25.09.2025 NCC : Yes/No Index : Yes/No Internet:Yes skn 3/5 https://www.mhc.tn.gov.in/judis
W.P(MD)No.26654 of 2025 To
1. Tamil Nadu Power Distribution Corporation Limited (TNPDCL) 10th Floor, 144, Anna Salai, Chennai - 600 002, Represented by its Chairman and Managing Director. 2. The Superintending Engineer Madurai / Metro Electricity Distribution Circle, Tamil Nadu Generation and Distribution Corporation Limited, Madurai. 4/5 https://www.mhc.tn.gov.in/judis
W.P(MD)No.26654 of 2025 P.T.ASHA, J. skn
Writ Petition(MD)No.26654 of 2025 and W.M.P(MD)No.20655 of 2025
25.09.2025 5/5 https://www.mhc.tn.gov.in/judis