HIGH COURT OF JAMMU & KASHMIR AND LADAKH AT JAMMU
WP(C) No. 3093/2025 CM No. 7078/2025
M/S AAA Construction & Builders
…..Petitioner
Through: Mr. M.K. Raina, Advocate
Vs
UT of J&K & Ors. .….Respondents
Through: Mr. Ravinder Gupta, AAG
CORAM: HON’BLE MR. JUSTICE RAHUL BHARTI, JUDGE
ORDER (07.11.2025)
01. The petitioner is premature in its writ petition by its apprehension that the tender finalization committee or for that matter the respondent No. 2-Chief Engineer, PMGSY (JKRRDA), Jammu would entertain the financial bids of the non-eligible bidders who otherwise have qualified the technical bid stage but their documents are not fair and square.
02. It is for the respondent No. 2 or for that matter Contract Evaluation Committee, if there is any, to be best judge of the situation with respect to the eligibilities of the bidders participating in the financial bid as this Court is not meant for acting as a messenger for the petitioner for Serial No. 146 Supplementary List-1
2
WP(C) No. 3093/2025
registering reminder to the respondent No. 2 that due diligence is to be adopted for evaluating the financial bids.
03. The writ petition is, therefore, dismissed without prejudice to the rights of the petitioner to assail the outcome of the financial evaluation, in case, the petitioner loses out in that process.
(RAHUL BHARTI) JUDGE JAMMU
07.11.2025
SUNIL
Whether the order is speaking ? : Yes/No
Whether the order is reportable ? : Yes/No