( 2025:HHC:33308 )
IN THE HIGH COURT OF HIMACHAL PRADESH SHIMLA
Execution Petition No.613 of 2024 Date of Decision: 24.09.2025 __________________________________________________
Ram Dayal and another
....Petitioner
Versus
State of H.P. and others
…Respondents ___________________________________________________ Coram
Hon’ble Mr. Justice G.S. Sandhawalia, Chief Justice Hon'ble Mr. Justice Ranjan Sharma, Judge
Whether approved for reporting? 1
For the petitioner: Mr. Ajay Sharma, Advocate.
For the respondents: Ms. Priyanka Chauhan, Deputy Advocate General, for the respondents.
G.S. Sandhawalia, Chief Justice (Oral)
Counsel for the State has placed on record communication dated 23.09.2025, wherein notification under Section Under Section 19 of Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 (RFCTLARR Act, 2013) has been issued. It is further mentioned that process of preparation of draft award is in progress and notice under Section 23 of the Act has
1 Whether reporters of Local Papers may be allowed to see the judgment?
2 also been served. Copy of notification dated 02.05.2025 has also been appended.
2.
Keeping in view the above, we are of the considered opinion that the compliance has been done, since issue was to initiate the process of acquisition for the construction of Bhatta Kufar-Chakdyal Road.
3.
Resultantly, the present petition has been rendered infructuous and disposed of as such.
4.
Pending applications, if any, also stand disposed of accordingly.
( G.S. Sandhawalia )
Chief Justice
24th September, 2025
( Ranjan Sharma ) (priti)