Neutral Citation No. - 2025:AHC:33458-DB Court No. - 21 Case :- WRIT - C No. - 4183 of 2025 Petitioner :- Vinod Kumar Sharma Respondent :- State of U.P. and Another Counsel for Petitioner :- Aradhana Pandey,Manoj Kumar Pandey Counsel for Respondent :- Namman Raj Vanshi,C.S.C.,Shiv Prakash Gupta Hon'ble Manoj Kumar Gupta,J. Hon'ble Jayant Banerji,J.
1. The case of the petitioner is that he was allotted Plot No.A- 852 area measuring 162 sq. mts. in Shraddhapuri Phase-II, Meerut by Meerut Development Authority, Meerut in the year
2003. The petitioner claims that he has deposited the entire amount in terms of the allotment letter within one year, but the Meerut Development Authority failed to execute the sale-deed and deliver possession of the plot to the petitioner. The petitioner, therefore, filed a complaint against the Meerut Development Authority, Meerut before District Consumer Grievance Redressal Forum, Meerut and the complaint was
disposed of directing payment of simple interest at the rate of 16% per annum on the amounts deposited by him until the date of delivery of possession. Apart from it, the District Forum also awarded damages against the Meerut Development Authority, Meerut. The matter was carried in appeal by Meerut Development Authority, Meerut. The State Consumer Grievance Redressal Forum upheld the order of the District Forum, but only reduced the interest from 16% to 10% per annum.
2. Learned counsel for the Meerut Development Authority, Meerut points out that against the aforesaid order, the Meerut
Development Authority, Meerut went up in second appeal before the National Consumer Grievance Redressal Forum and its appeal was dismissed. Challenging the same, it has filed a petition, being Matter under Article 227 No.1628 of 2025, in which notice has been issued to the petitioner and the said petition is pending.
3. The prayer made in the instant writ petition is for a direction to Meerut Development Authority, Meerut to execute sale-deed in pursuance of the allotment letter in favour of the petitioner.
4. Learned counsel appearing for the Meerut Development Authority, Meerut has submitted that it has to be ascertained whether the petitioner has paid the entire amount under the allotment letter and whether there is any impediment in executing the sale-deed.
5. Having regard to the facts of the case and the submissions made, we are of the view that the interest of justice would be subserved in case the Meerut Development Authority, Meerut is
directed to pass a speaking order in respect of the prayer of the petitioner for execution of sale-deed in his favour.
6. Accordingly, we dispose of the instant writ petition with liberty to the petitioner to make a detailed representation before the Meerut Development Authority, Meerut alongwith true attested copy of the instant order. The Vice-Chairman of the Meerut Development Authority, Meerut will pass a speaking
order on the said representation within next four weeks.
Order Date :- 7.3.2025 SK (Jayant Banerji, J.) (Manoj Kumar Gupta, J.) Digitally signed by :- SUSHEEL KUMAR High Court of Judicature at Allahabad